Restart of Mount Boppy Gold Mine - Execution Update
Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide a
progress update on the restart of gold doré production from its 100% owned Mt Boppy
gold mine (“Mt Boppy”) located in the Cobar Basin, NSW (Figure 1).
Highlights
•
Manuka is executing a strategy to construct a fit-for-purpose processing and
gold doré production facility at its 100% owned Mt Boppy gold mine.
•
Previously, ore from Mt Boppy had been hauled to and processed at the
Company’s CIL plant located at the Wonawinta Silver Mine (“Wonawinta”)
150km south of Mt Boppy.
•
Mt Boppy is forecast to be a low capex (A$11.6M), high margin (~A$19M
EBITDA per annum) operation1.
•
Relocation of the existing 400kW ball mill located at Wonawinta to Mt Boppy
has commenced. The ball mill is surplus to requirements at Wonawinta where a
1800kW ball mill has been previously installed.
•
Acquisition of a second-hand Inline Pressure Jig (IPJ) and Intensive Leach
Reactor (ILR) has resulted in approximately A$850k savings versus that
originally budgeted. The purchased equipment is currently undergoing
refurbishment at Gekko Systems, the original equipment manufacturer.
•
The Company is currently investigating opportunities to increase milling
capacity and accelerate gold production at Mt Boppy.
•
The Company is targeting first gold production from Mt Boppy in Q4 2024.
Dennis Karp, Manuka’s Executive Chairman, commented:
“The execution of our plan to restart gold operations at Mt Boppy is well underway.
The opportunistic purchasing of selected second-hand processing equipment is
consistent with our low capex strategy that includes the leveraging and repurposing of
existing assets including the Wonawinta 400kW ball mill, diesel generators, 48-man
accommodation camp and mobile screening plant.
We look forward to providing regular updates to the markets as we progress towards
first gold production at Mt Boppy.
1 ASX Release 15 Apil 2024
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Figure 1: Location of Manuka’s Mt Boppy and Wonawinta Project within the Cobar basin.
Background
The Mt Boppy gold mine is an existing gold operation comprising a brownfields open pit
and associated historic ROM stockpiles, rock dumps and tailings.
In April 2024, Manuka announced a strategy whereby a fit-for-purpose processing and
gold production facility would be established at Mt Boppy for a capital cost A$11.6M to
generate an average EBITDA of ~A$19M per annum over an initial 5-year period2.
A sonic drilling program over the Main Rock Dump and Tailings Storage Facility 3
(“TSF3”) was completed in late 2023 which improved confidence in Resource3 grade
and ore type distribution and underpins the updated production strategy.
Previously, ore mined by Manuka at Mt Boppy had been hauled 150km to the CIL
process plant located at Wonawinta at a cost of ~A$27/t. The updated strategy of onsite processing is expected to save in the order of A$7M per annum.
2 ASX Release 15 Apil 2024
3 ASX Release 16 April 2024
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Project Execution
Manuka’s low capex strategy and base case production target at Mt Boppy is designed
around an annualised feed rate of ~230ktpa through Manuka’s existing 400kW ball mill
currently located at Wonawinta. The Company has commenced the relocation of the
ball mill and associated processing components at Wonawinta (Figure 2) and once
complete, will transport the equipment to Mt Boppy.
Figure 2: Photos showing dismantling of the 400kW ball mill and associated processing
infrastructure at Wonawinta in preparation for its relocation to Mt Boppy.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
The Company had originally included A$1.1M in its capital budget based on quotes from
Gekko Systems for a new Inline Pressure Jig and Intensive Leach Reactor. Manuka
was able to acquire these items via an auction for a total of A$266k resulting in an
A$850k capital saving (Figure 3). Both items are currently undergoing refurbishment at
Gekko Systems in Ballarat, Victoria.
Figure 3: Photos showing the second-hand Inline Pressure Jig (left) and Intensive Leach
Reactor (right) purchased by Manuka at auction.
In addition to the above items, Mt Boppy includes an existing 48-man camp (Figure 4)
and McCloskey R230 “Reclaimer” mobile screening plant (Figure 5) to further manage
project capex and derisk project execution.
Figure 4: Photo of the existing camp located on site at Mt Boppy.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Figure 5: Photo of the McCoskey R230 ‘reclaimer’ mobile screening plant at Mt Boppy.
Additional Workstreams
The sonic drill program over the Main Rock Dump and Tailings Storage Facility 3
completed by Manuka in late 2023, and the subsequent Mineral Resource Estimate4
update, provided the Company with further confidence in grade and ore type distribution
throughout the Resource. To further derisk the commencement of production, the
Company intends to undertake a second round of sonic drilling during Q4 2024 to
provide additional grade control covering the first two years of mining from the Main
Rock Dump.
Furthermore, the Company is currently undertaking additional metallurgical testwork on
samples recovered from the completed sonic drill program to further optimise process
operating parameters ahead of production. Initial results of this testwork will be received
and interpreted over the coming month.
The demarcation of oxide and fresh ores within the Main Rock Dump (Figure 6) and the
results of the metallurgical testwork will support the Company’s consideration of
adopting a parallel processing stream strategy as a means to increasing process plant
throughput and accelerating gold production.
The Company is currently investigating the cost benefit and feasibility of this opportunity
and aims to provide an update to the market in the coming months. Importantly, any
increase in processing throughput would not occur immediately and associated capex
would be funded via cashflows from the project.
4 ASX Release 16 April 2024
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Figure 6: Outline of Oxide, Fresh and Rock Dump Tailings Ore within the Main Rock Dump
Corporate Update
The Company is well progressed on a process to refinance the existing TransAsia
Private Capital Limited (“TransAsia”) debt facility. The TransAsia facility was originally
drawn in 2019 and utilised to refurbish the 1Mtpa Wonawinta Process plant and bring it
out of care and maintenance for processing of gold and silver ore throughout 2020 to
2023.
BurnVoir Corporate Finance has been appointed to manage the refinancing process.
This announcement has been approved for release by the Board of Manuka Resources
Limited.
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
0412 268 114
Media Contact
Ben Henri
M+C Partners
0473 246 040
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
About Manuka
Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration company with
key gold and silver assets located in the Cobar Basin, central west New South Wales and
offshore vanadium bearing iron sands in the South Taranaki Bight of New Zealand. These
projects include:
The Mt Boppy Gold Mine (Cobar Basin, NSW)
The Mt Boppy gold mine is located 43 km east of Cobar, in the Central West region of New
South Wales. The current Mt Boppy Mineral Resource is estimated at 4.3Mt at 1.19 g/t Au5 and
comprises a mix of oxidised and transitional/fresh in-ground mineralisation, mineralised rock
dumps and mineralised tailings.
The Company has to date processed its stockpiles and gold mineralised waste product through
its Wonawinta plant. Manuka are currently pursuing a strategy of establishing of a fit-forpurpose, on-site crush-screen-mill-float facility to enhance the economics of the Mt. Boppy Mine
and the value of near-mine prospects. The Mt Boppy site includes a 48-person mine camp and
is fully permitted for the proposed processing plant and on-site production.
The Wonawinta Silver Mine (Cobar Basin, NSW)
Previously Australia’s largest primary silver producer, Wonawinta produced approximately 3
million ounces of silver during 2012-2013, and an additional 500,000oz of silver in 2022. The
mine hosts a significant Resource6 - including stockpiles and shallow oxide material, Wonawinta
contains total Resources of 38.8 million tonnes at 42 g/t Ag for 52.4 million ounces. Within this
there is a higher-grade component of 4.5 million tonnes at 97 g/t Ag for 14 million ounces.
The Wonawinta processing plant has a nameplate capacity of approximately 850,000 tpa. The
Company is reviewing the potential of recommencing operations at Wonawinta, taking
advantage of the strengthening silver price environment.
The Mt Boppy Gold mine (left) & Wonawinta Silver Mine(right)
5 ASX Release 16 April 2024
6 ASX release 1 April 2021
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
The Taranaki VTM Project (South Taranaki Bight, New Zealand)
Manuka is the 100% owner of the Taranaki VTM (vanadium titanomagnetite) Iron Sands Project.
The Project sits in the lowest quartile of the iron ore production cost curve.
The Taranaki VTM Project comprises a 3.2Bt Resource7 at 10.17% Fe2O3, 1.03% TiO2 and
0.05% V2O5 (1.6Mt V2O5) ranking it as one of the largest drilled vanadium projects globally.
The Project is located 22 km to 36 km offshore in New Zealand’s EEZ, or Exclusive Economic
Zone, outside the 12 nautical limit from the shoreline, in waters ranging between 20 to 50 metres
depth and has a granted mining license, MP55581, permitting production of 5Mtpa. On granting
of final government approvals to operate the Company will complete its Bankable Feasibility
Study on the Project.
Location of Taranaki VTM Project
7ASX release 1 March 2023
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Compliance Statements
The information in this presentation that relates to previously reported Exploration Results, Exploration
Targets, Mineral Resources, Ore Reserves, Production Targets and Financial Forecasts is extracted from
the Company’s ASX announcements noted in the text of the presentation and are available to view on
the Company’s website. The Company confirms that, other than mining depletion, it is not aware of any
new information or data that materially affects the information included in the original announcements
and, in the case of estimates of Mineral Resources and Ore Reserves, that all material assumptions and
technical parameters underpinning the estimates in the relevant announcement continue to apply and
have not materially changes. The Company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially altered.
Important Information
This report includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other
similar expressions are intended to identify forward-looking statements. Such statements involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company and which may cause actual results, performance or achievements to differ
materially from those expressed or implied by such statements. Forward-looking statements are provided
as a general guide only and should not be relied on as an indication or guarantee of future performance.
Given these uncertainties, recipients are cautioned to not place undue reliance on any forward-looking
statement. Subject to any continuing obligations under applicable law, the Company disclaims any
obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in
this report to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based. No Limited Party
or any other person makes any representation, or gives any assurance or guarantee that the occurrence
of the events expressed or implied in any forward-looking statements in the report will occur.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Share your feedback
Discover