Taranaki VTM Project - Pre-Feasibility Study Presentation
Released
Released
Announcement PDF
23 April 2025
Taranaki VTM Project
Fast Track application
lodged 15 April 2025
Pre-Feasibility Study Presentation
A Nationally Significant Project providing shareholders
with strategic exposure to Iron Ore and Critical Minerals
Vanadium and Titanium in New Zealand
Disclaimer
This disclaimer applies to this presentation and the information contained in it (the Presentation). By reading
this disclaimer you agree to be bound by it. The Presentation has been prepared by Manuka Resources Limited
and relates to its subsidiaries, related parties and any new assets or entities subsequently acquired or
incorporated (collectively the Company). The Presentation was prepared on 23 April 2025 and the information in
it is subject to change without notice.
Purpose
The Presentation is for information purposes only and is an overview of the Company and its assets at the time
of preparation. This Presentation does not contain all information necessary to make an investment decision or
that would be required in a prospectus or product disclosure statement prepared in accordance with the
requirements of the Corporations Act 2001 (Cth) (Corporations Act). The Presentation is of a general nature
and does not purport to be complete or verified by the Company or any other person.
Distribution outside Australia
Distribution or release of this document outside Australia may be restricted by law. This document may only be
distributed or released to a person that is not in the United States except as permitted under the U.S. Securities
Act. Persons who come into possession of this document who are not in Australia should seek advice on and
observe any such restrictions. Any failure to comply with such restrictions may constitute a violation of applicable
securities laws.
Not an offer or financial product advice
The Presentation does not constitute an offer, invitation, solicitation or recommendation with respect to the
purchase or sale of any security in the Company nor does it constitute financial product advice. The Presentation
is not a prospectus, product disclosure statement or other offer document under Australian law or under any
other law. The Presentation has not been filed, registered or approved by any regulatory authority in any
jurisdiction. The Presentation is not intended to be relied upon as advice or a recommendation to investors and
does not take into account the investment objectives, financial situation, taxation situation or needs of any
particular investor.
An investor must not act on the basis of any matter contained in the Presentation and must make its own
assessment of the Company and conduct its own investigations and analysis. Investors should assess their own
individual financial circumstances and consider talking to a financial adviser, professional adviser or consultant
before making any investment decision. Neither this Presentation nor anything contained in it forms the basis of
any contract or commitment and no agreement to subscribe for securities will be entered into on the basis of this
Presentation.
No guarantee, representation or warranty
While reasonable care has been taken in relation to the preparation of the Presentation, none of the Company or
their respective directors, officers, employees, contractors, agents, or advisers nor any other person (Limited
Party) guarantees or makes any representations or warranties, express or implied, as to or takes responsibility
for, the accuracy, reliability, completeness or fairness of the information, opinions, forecasts, reports, estimates
and conclusions contained in the Presentation. No Limited Party represents or warrants that the Presentation is
complete or that it contains all information about the Company that a prospective investor or purchaser may
require in evaluating a possible investment in the Company or acquisition of shares in the Company. To the
maximum extent permitted by law, each Limited Party expressly disclaims any and all liability, including, without
limitation, any liability arising out of fault or negligence, for any loss arising from the use of or reliance on
information contained in the Presentation including representations or warranties or in relation to the accuracy or
completeness of the information, statements, opinions, forecasts, reports or other matters, express or implied,
contained in, arising out or derived from, or for omissions from the Presentation including, without limitation, any
financial information, any estimates or projections and any other financial information derived therefrom.
Forward-looking statements
The Presentation includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as “expect”,
“should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other similar
expressions are intended to identify forward-looking statements. Such statements involve known and unknown
risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the
Company and which may cause actual results, performance or achievements to differ materially from those
expressed or implied by such statements. Forward-looking statements are provided as a general guide only, and
should not be relied on as an indication or guarantee of future performance. Given these uncertainties, recipients
are cautioned to not place undue reliance on any forward-looking statement. Subject to any continuing
obligations under applicable law, the Company disclaims any obligation or undertaking to disseminate any
updates or revisions to any forward-looking statements in the Presentation to reflect any change in expectations
in relation to any forward-looking statements or any change in events, conditions or circumstances on which any
such statement is based. No Limited Party or any other person makes any representation, or gives any
assurance or guarantee that the occurrence of the events expressed or implied in any forward-looking
statements in the Presentation will occur.
Past performance
Past performance is not indicative of future performance and no guarantee of future returns is implied or given.
Previously reported information
The information in this presentation that relates to previously reported Exploration Results, Exploration Targets,
Mineral Resources and Ore Reserves is extracted from the Company’s ASX announcements noted in the text of
the presentation and are available to view on the Company’s website. The Company confirms that, other than
mining depletion, it is not aware of any new information or data that materially affects the information included in
the original announcements and, in the case of estimates of Mineral Resources, Ore Reserves, Production
Targets and Financial Forecasts, that all material assumptions and technical parameters underpinning the
estimates in the relevant announcement continue to apply and have not materially changes. The Company
confirms that the form and context in which the Competent Person’s findings are presented have not been
materially altered.
2
About the Taranaki
VTM Project
✓ 100% Owned by Manuka’s subsidiary
Trans-Tasman Resources (“TTR”)
✓ Granted Mining Permit MMP55581 and
exploration permit MEP54068
✓ 3.2Bt Resource1 of Vanadiferous
Titanomagnetite (“VTM”) iron sands
located in the shallow waters of the
South Taranaki Bight, New Zealand
✓ NZD$85m spent on Technical and
Environmental Studies since 2009
✓ Updated Pre-Feasibility Study
completed (2025) showing an NPV10
of US$1.26B and IRR of 39%2
1.
2.
ASX Release 1 March 2023
ASX Release 26 March 2025
Location of the Taranaki VTM Project with respect to Mineral
Resource outline, granted Mining Permit MMP55581 (within New
Zealand’s Exclusive Economic Zone) and Exploration Permit
MEP54068 (within New Zealand Territorial Waters)
3
Pre-Feasibility Study
Highlights
ASX Release 26 March 2025
3.2Bt Mineral Resource
NPV10
US$1.26B
IRR 39%
US$312M
EBITDA
per annum
Large World Class Iron Sands Deposit, South Taranaki Bight NZ
Initial 20-year Mine Life
with material mine life extension opportunities
4.9Mtpa 56-57%Fe
+ Vanadium and Titanium (Critical Minerals) co-products
US$27.20/t C1 Cost
excluding any co-product credits
US$602M Project Capex
(inclusive 14% contingency)
National Significance
Project included in NZ Government’s Fast Track Approvals Act 2024
Mt Taranaki, NZ
Macroeconomic assumptions include 13.7% discount to a flat benchmark Fe concentrate pricing of US$90/t CFR China, V2O5 co-product
pricing of US$5.45/lb (multiplied by a 77% third party recovery rate and 50% payability) and Capesize freight rates of US$10/t.
4
Mineral Resource1 and
Production Target2
Resource
Bt
Fe2O3
TiO2
V2O5
Indicated
1.4
10.37%
1.05%
0.05%
Inferred
0.5
8.81%
0.90%
0.04%
MMP55581
1.9
9.99%
1.01%
0.05%
Indicated
0.7
10.61%
1.07%
0.05%
Inferred
0.6
10.26%
1.04%
0.05%
MEP54068
1.3
10.44%
1.05%
0.05%
Total
3.2
10.17%
1.03%
0.05%
Information relating to Exploration Results, Sampling Techniques and Data, and
Mineral Resources for the Taranaki VTM Project is extracted from the
announcement titled ‘Maiden Vanadium Resource at Taranaki VTM Iron Sand
Project” dated 1 March 2023 and available to view on the Company’s website.
The Company is not aware of any new information or data that materially affects
the information used to compile the 2023 Mineral Resource and all material
assumptions and technical parameters underpinning the estimates in the relevant
market announcements continue to apply and have not materially changed.
1.
2.
ASX Release 1 March 2023
ASX Release 26 March 2025
Initial Mine Plan of 20 Years is based on mining 1Bt of
iron sands in granted Mining Lease MMP55581 to produce
4.9Mt pa of VTM Concentrate2
Total Resources within MMP55581 comprises 1.9Bt of
75% Indicated and 25% Inferred Resources
Mining for the first 13 years will focus on the Cook South
block of the Resource which comprises 95% Indicated
Resources and 5% Inferred Resources1
Metallurgical assumptions supporting the Production
Target are based Davis Tube Recovery and bulk
samples Pilot Plant Test Work undertaken on samples
collected from 726 drill holes across the Resource1,2
The Production Target underpinning PFS financial forecasts comprises 75% Indicated and 25% Inferred
Resources. Further evaluation work and appropriate studies are required to establish sufficient confidence
that this target will be met. There is a low level of geological confidence associated with Inferred
Resources and there is no certainty that further exploration work will result in the conversion of Inferred
Resources to Indicated Resources or return the same grade and tonnage distribution. The Mineral
Resource underpinning the Production Target has been prepared by a Competent Person in accordance
with the requirements in the JORC Code.
5
Operations
Integrated Mining Vessel
✓ Iron sands will be mined using seabed
crawlers at a rate of 50Mtpa and
pumped as a slurry to an Integrated
Mining Vessel (“IMV”) on the surface
✓ Onboard the IMV, the sand will be
screened, magnetically separated and
ground, before a final magnetic
separation to produce a VTM
concentrate grading ~57% Fe, 0.50%
V2O5 and 8.4% TiO2
✓ The Project is scheduled to produce
VTM concentrate at a rate of 4.9Mtpa
over an initial period of 20 years
✓ The 45Mt balance of the mined sand will
be returned continuously to the seabed
where it will be fully restored to its
natural state within two years
A mobile seabed crawler has
been selected as the preferred
sediment extraction technology to
be integrated into the IMV
Proven and tested technology is
very similar to the De Beers Marine
extraction equipment operated
offshore Namibia for over 30 years
6
Project Costs
✓ Operating costs have been estimated on
the basis that all primary mining and
process operations will be carried out by
the Company
✓ All transfer and support operations will be
contracted out to third parties
✓ Total C1 Operating Costs are forecast
to be US$27.20/t VTM concentrate
OPEX Costs by Input Item
Contractor Costs
7.00
Fuel
8.12
Repairs & Maintenance
2.04
Labour
6.27
Insurance
0.57
Other Costs (Misc.)
2.20
Enviro Monitoring & Training
1.00
Total Opex
27.20
The Opex estimates of this PFS are considered to be ±30% order of accuracy current at the first quarter of 2025.
Capex Cost by Component
(before including Vanadium Credits)
✓ Total Capital Cost for the Project are
IMV
estimated to be US$602M including 14%
(US$84.4M) of contingency
Process
✓ NZ$2M included to establish a dedicated
Auxiliary
employee training facility in Hāwera and
NZ$3.9M for an environmental monitoring
and research vessel
US$/t Concentrate
Mining Systems
Management
Item
Hull
Equipment
Integration
Process Plant
Dewatering
Crawler
Power Generation
Desalination
Procurement, Management,
Engineering
US$M
61.2
38.0
54.1
183.9
18.1
112.0
74.5
26.1
34.4
Total Capex
602.2
included contingency
84.4
The Capex estimates of this PFS are considered to be ±30% order of accuracy current at the first quarter of 2025.
7
National Significance
✓ New Zealand’s stated objective is to
double mineral export earnings from
NZ$1.5B to NZ$3B per annum over
the next decade1
✓ The Taranaki VTM Project is forecast
to generate NZ$854M export revenue
per annum representing over 50% of
the targeted increase
✓ Both vanadium and titanium have
recently been named on New
Zealand’s Critical Minerals List
The Project was included in Schedule 2 (projects to be
directly referred to an Expert Panel) of the recently
passed New Zealand Fast Track Approvals Act 20242
The Company submitted its application on 15 April
2025 and has commenced the Fast Track approvals
process
“The Project will deliver substantial benefits to the Taranaki
and Whanganui regions, including:
•
Over 300 new full-time local jobs;
•
1,123 jobs in the region;
•
NZ$238M p.a. expenditure injected into the local economy.”
New Zealand Institute of Economic Research
✓ The Project will support the NZ
Government delivering on its Critical
Minerals List and Minerals Strategy for
NZ to 2040 policy objectives
1.
2.
https://www.odt.co.nz/business/govt-aims-double-mining-exports-2035
https://environment.govt.nz/acts-and-regulations/acts/fast-track-approvals
8
Corporate Summary
Share Price History
Capital Structure
Shares Outstanding
810M
Options Outstanding
206M
Share Price
A$0.039
Market Capitalisation
A$31.6M
Cash
A$2.0M
As at 31 December 2024
Debt Outstanding
~A$38.6M
As at 31 December 2024
•
•
A$19.1M TransAsia Pty Ltd - Senior Debt Facility
A$12.5M Tennant Metals SA Pty Ltd - Trade Finance Facility
Ownership Breakdown:
As at 31 December 2024
Share Price Catalysts for 2025:
✓ Final Fast Track Approval of the Taranaki VTM Project
✓ Commencement of the VTM Project Bankable Feasibility Study
14%
✓ Continued strength in the Gold and Silver markets
✓ Refinance of the TransAsia Debt Facility
✓ Secure non-dilutive funding to support Restart of Precious
Metal Production in the Cobar Basin
86%
Board & Management
Other
✓ Near Term Gold & Silver Production from Mt Boppy and
Wonawinta
9
Thank you