Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
30 October 2023
ASX: MKR
September 2023 Quarterly Activities Report
Key Points
• Mt Boppy gold production gained strong momentum during Quarter
with Sales revenue of $6.5m including $3.86m in September alone.
• Quarterly gold sales of 2,118oz (& 11,887oz Ag).
• Production well ahead of sales with 2,762oz Au and >13koz Ag
produced plus a further 1,260oz Au in circuit at Sept 30, worth
~$3.75m.
• Average grade of material screened was ~1.7g/t Au.
• Gold recoveries increased at rate of ~20% per month over the
Quarter: July 780oz; Aug 904oz; and Sept 1,078oz.
• Gold recoveries for October will be >1,300oz Au.
• Exploration drilling at the Pipeline Ridge prospect has been
prioritised commencing in January 2024.
• Mt Boppy JORC Resource update announced in August1 with a
further upgrade expected in the March Quarter.
• At the Taranaki VTM Project, Manuka continues to await the regranting of EPA’s environmental consents.
Dennis Karp, Manuka’s Executive Chairman noted: “The Company is now realising the
benefits of the Mt Boppy gold bearing, screening program and gold production in October
has continued to grow. The Company expects a substantially stronger December Quarter
in terms of both production and operating cash flow. The continuation of the Mt Boppy
1
ASX release 24 August 2023
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
screening program and its forecast profitability will provide a sound base for Manuka to
thrive and more aggressively explore its array of identified opportunities.”
Overview of the September Quarter 2023
Mt Boppy
The September Quarter was the first full quarter for the Mt Boppy screening program. A
total of 114,214 of Mt Boppy waste and dumps were screened in the September Quarter,
generating 77,990t of <8mm material and 6,139t of 8-20mm material (with the balance going
to waste). Weather conditions were favourable throughout the quarter with any weather
induced downtime allowing for plant maintenance, so that plant availability was not unduly
impacted. Record daily mill throughput of 1,636t (total product) was achieved during
September.
Production at the Wonawinta plant for the quarter was 66,987t at an average head grade of
~1.7g/t. A highly experienced processing manager (Dieter Englehardt) was hired during the
period which has resulted in improved plant performance in certain areas already. The
company is currently developing a plant operating strategy (campaign style operations)
which should result in a significant decrease in operating costs whilst not impacting monthly
processing rates. The board will review the final plan and its potential implementation over
the next month.
A new larger McCloskey screen (R230) was mobilised at site and commissioned in midSeptember. This screen has a 50% larger surface area than the original screen resulting in
greater feed and product tonnes being achieved.
Gold poured during the period was 2,118oz with a further 1,260oz of gold in the circuit as at
the end of September.
Operating Summary
Summary
Tonnes Milled
Gold in Circuit (30-09-23)
Gold Recovered
Gold Sold
Silver Sold
Gold Recoveries
Revenues
t
oz
oz
oz
oz
AUD $’000
Sept Quarter
Financial Year (YTD)
66,987
1260
2762
2118
11,887
76.5%
6,539
66,987
1260
2762
2118
11,887
76.5%
6,539
Taranaki VTM Project
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Manuka’s wholly owned subsidiary, Trans-Tasman Resources Limited (TTR), was granted
Mineral Mining Permit MMP55581 located 22km to 36km offshore in New Zealand’s South
Taranaki Bight (STB) in 2014. In 2017 the NZ Environmental Protection Authority (EPA)
granted the environmental marine and marine discharge consents (Consents) to operate.
The grant of these Consents was then subject to third party legal challenge. Judgments in
the High Court in 2018, the Court of Appeal in 2020 and particularly the Supreme Court
(SC) in 20212 identified apparent information deficits, summarised the legal deficiencies of
the EPA’s Decision Making Committee’s (DMC) Consents grant and the legal framework for
the DMC to address when the grants are reconsidered.
The SC referred the Consents back to the EPA for reconsideration by its DMC on five
narrowly defined points of law. The new DMC reconvened in March 20233 and requested
TTR provide expert evidence to satisfy the SC’s ruling on information deficits. In May and
August 2023 TTR provided the expert evidence to the DMC to satisfy the SC’s requirements
and legal tests to reissue the Consents. These expert reports concluded the proposed VTM
mineral recovery in STB will avoid material harm, will favour caution and environmental
protection in relation to the effects of the proposed mining operations and resulting
sedimentation on biota in the STB including no adverse ecological effects on marine
mammals and seabirds. Accordingly, there are no aspects of TTR’s 2017 environmental
Consents that are an impediment to having them re-approved by the reconvened DMC4.
In parallel with this formal EPA engagement process, TTR intends to commission additional
metallurgical test work to optimise the flowsheet for processing of the VTM concentrate
(including the recovery of vanadium and titanium) during 2023 and 2024 and undertake
marketing (and related) studies building on work completed during the Pre-Feasibility Study
(PFS).
Globally VTM titanomagnetite iron sands are in strong demand as feed for electric arc
furnaces (EAF) to produce low carbon “green steel”. EAF steel making burns 50% less coal,
reduces emissions by more than 45% in the steel making process and sets the platform for
meeting net zero goals by 2050. Vanadium, apart from its widespread and increasing
application as a steel alloying element to strengthen steel, is rapidly building demand as an
electrolyte in vanadium redox flow batteries (VRFB) which are fast becoming the preferred
IP for large grid-scale high-capacity battery stations to store renewable energy due to their
longevity and fire safety characteristics, ahead of all competing technologies.
Australia is now building its first 850Mw, with 1,680Mwh capacity, VRFB Waratah Super
Battery at the former Munmorah coal fired power station in NSW to drive Australia’s
transition to a low carbon economy.
With concerns over the sovereign security of vanadium supply from key producing nations
China (comprising 55% of global production), Russia (20% of global production), Brazil
(15%) and South Africa (10%), vanadium now has “critical mineral” status in Australia, USA
2 Judgement delivered 30 September 2021
Refer EPA Public consultation disclosures at www.epa.govt.nz/public-consultations/in-progress/trans-tasman-resourceslimited-2016/
4 Refer ASX announcement 1 August 2022
3
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
and the EU. The demand for VTM concentrate for EAF low carbon green steel production
together with the rapidly growing demand underpinning rising prices for vanadium, suggests
the potential of our Taranaki VTM Project, hosting one of the largest known vanadium
resources in the world with 1.6Mt contained V2O5 metal, will attract the competitive capital
investment and metal producer offtake interest required to develop the project.
The Taranaki VTM Project, when in production with an estimated annual production of
10,000 tonnes of vanadium metal, will make Manuka one of the leading vanadium producers
in the world and propel NZ into the third largest producer of the metal after China and
Russia.
Resource Growth and Exploration Outlook
The Company’s geological team has continued to implement the exploration work
programmes established from the Q1 2023 Strategic Review. The MKR Resource Triangle
(Fig. 1) shows the current classification of the exploration targets, and those highlighted on
which work was undertaken during Q2 and Q3 2023.
Figure 1
The resource base at Mt Boppy outside of the in-pit resources continues to expand. This
has been achieved through continued bulk sampling of the Mt Boppy Main Waste dump
material and screening into a sub 10mm fraction, which comprise approximately 40-50% by
mass. The Mt Boppy waste dump is estimated to contain approximately 3.92 Mt of variably
mineralised waste rock and old tailings material. Of this, between 1.6-1.9Mt is targeted as
a screened product. Systematic excavation and screening of the Main Waste dump is
steadily building incremental (currently over 216kt) screened product resources that are
viable to truck to the Wonawinta plant. This material will be processed after completion of
current mining of the Mt Boppy ROM pad and rock dump during the December Quarter.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Bulk sampling of the McKinnons low grade rock dumps has continued intermittently during
the quarter and are planned to be completed during the December quarter.
MKR Mineral resources at Mt Boppy were updated during the quarter to include the rock
dump and tailings evaluations and are summarised in Table 1.
Table 1
Other work programmes that have been progressed include,
•
•
•
•
•
Completion of the design of deeper diamond drilling to test and potentially
establish incremental resources at Mt. Boppy;
Continued geological modelling and assessment of historic drilling data of the
Pipeline Ridge base metal – gold deposit, assessment of available diamond core.
The initial drilling programme is now scheduled for early 2024;
Post a tender process a drilling contractor has been appointed for the Pipeline
Ridge and Mt Boppy Deeps drilling programmes;
Completion of a detailed regional geophysics synthesis of the Wonawinta ML
and exploration tenements, including conducting a merged data reinterpretation
of all available magnetic data and a revised IP interpretation for the McKinnons
gold prospect; and
Continued analysis and reorganisation of the Company’s extensive drilling and
geochemical sampling database.
Drill programmes for 2024 have been scoped in-line with prioritisation of the targets on
Figure 1 with encouraging engagement with local drilling contractors for these activities.
Exploration of the Pipeline Ridge prospect and Mt Boppy mine deeps drilling are priority
targets, and these activities are expected to start during Q1 2024.
Cashflow and Hedging
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Manuka reported Operating cash flow for the Quarter of ($2.0) million. (It is worthwhile
noting that Net Revenue for September alone was $3.825m while unaudited Operating
Costs on a per month basis range between A$2.8-2.9m). Gold in circuit as at the end of the
Quarter was 1260oz gold (this is gold recovered in the Wonawinta circuit but not yet sold).
The Company did not have any open hedge contracts as at 30 September 2023.
The principal amount outstanding at Quarter end to the Company’s senior secured lender,
TransAsia Private Capital (TA) was US$8.0 million. During the quarter the Company
negotiated an extension of the facility and this amount is due in a single repayment on 30
September 2024.
Total borrowings as at 30 September 2023 were A$28.7 million. Unused facilities available
at Quarter end were A$664,000 and the cash balance was $155,251. Furthermore, there
was another A$3.4 million equivalent of gold in circuit.
In accordance with ASX Listing Rule 5.3.3, during the quarter, the Company made cash
payments of $0.174 million to related parties and their associates (refer items 6.1 and 6.2
of the Appendix 5B). This was the aggregate amount paid to the directors including salary,
directors’ fees, consulting fees and superannuation.
Mining Exploration Activities
In accordance with ASX Listing Rule 5.3.1 cash outflows for the quarter in relation to
exploration and evaluation activities were $0.282 million (refer Item 2.1(d) of the Appendix
5B) and predominantly comprised expenditure on:
•
Continued bulk sampling of gold mineralised material continued at Mt Boppy on
both the ROM and Main waste dump. This sampling will be used to generate a
resource report for these areas in the current quarter. Initial bulk sampling also
commenced on the former McKinnons gold mine waste dump;
•
Assessment of the deeper mineralisation in the Mt Boppy orebody continued
along with further inspection of historic drill core. Several deep boreholes are
planned for the current quarter to build on the current known resource; and
•
Further geophysical analysis resulted in all Canbelego historic magnetic data
being merged into a single database, reprocessed and filtered. A number of
untested geophysical targets emerged from this study and will be progressed in
the next two quarters.
Mining Development Activities
In accordance with ASX Listing Rule 5.3.2 cash outflows for the quarter in relation to mining
development activities were $67,000 (refer items 1.2(b) and 2.1(f) of the Appendix 5B).
These outflows relate to continued screening activities and mobile equipment at Mt Boppy.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Mining Production Activities
In accordance with ASX Listing Rule 5.3.2 cash outflows for the quarter in relation to mining
production activities were $4.60 million (refer Item 1.2(c) of the Appendix 5B) and comprised
the following:
Crushing contractors
$0.84 million
Hauling contractors
$0.54 million
Processing
$3.22 million
Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter
ended 30 September 2023.
Wonawinta Silver Project tenements are located approximately 90 kilometres to the
south of Cobar, NSW, and comprises one (1) granted mining lease and seven (7)
granted exploration licences as below, plus processing plant and associated
infrastructure.
Tenement
ML1659
EL6482
EL7345
EL6155
EL6302
EL7515
EL6623
EL8498
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Mt Boppy Gold Project tenements are located approximately 45 kilometres east of
Cobar, NSW, adjacent to the Barrier Highway. The Project comprises four gold
leases, two mining leases, one mining purpose lease and one exploration licence
which encompasses the MLs and extends the project area to the south.
Tenement
GL3255
GL5836
GL5848
GL5898
ML311
ML1681
MPL240
EL5842
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Taranaki VTM Iron Sand Project tenements are located offshore in the South
Taranaki Bight of the North Island, New Zealand. Tenements acquired as a result of
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
the acquisition5 of TTR comprise one granted mining permit and one granted
exploration permit.
Tenement
MMP55581
MEP54068
Percentage held / earning
100%
100%
Change during Quarter
-
There were no tenements disposed of during the Quarter.
5 ASX disclosure 11 November 2022
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
This announcement has been approved for release by the Directors of Manuka Resources Limited.
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
02 7253 2020
Media Contact
Angela East
M+C Partners
0428 432 025
Important Information
This report includes forward-looking statements and comments about future events, including the Company’s expectations about
the performance of its businesses. Forward-looking words such as “expect”, “should”, “could”, “may”, “predict”, “plan”, “will”,
“believe”, “forecast”, “estimate”, “target” or other similar expressions are intended to identify forward-looking statements. Such
statements involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company and which may cause actual results, performance or achievements to differ materially from those
expressed or implied by such statements. Forward-looking statements are provided as a general guide only and should not be
relied on as an indication or guarantee of future performance. Given these uncertainties, recipients are cautioned to not place
undue reliance on any forward-looking statement. Subject to any continuing obligations under applicable law, the Company
disclaims any obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in this report
to reflect any change in expectations in relation to any forward-looking statements or any change in events, conditions or
circumstances on which any such statement is based. No Limited Party or any other person makes any representation, or gives
any assurance or guarantee that the occurrence of the events expressed or implied in any forward-looking statements in the
report will occur.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
About Manuka Resources Limited
Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration company with key assets
located in the Cobar Basin, central west New South Wales. In addition to its recent acquisition of TransTasman Resources Limited owner of the Taranaki VTM Project, it is the 100% owner of two fully permitted
mining projects, one gold and one silver, both within the Cobar Basin, which include the following:
▪
Gold - Mt Boppy Gold mine, 48-person mine camp and neighbouring tenements, hosting an existing
open pit mineral resource6 and combined ROM, waste and tailings material all of which lend
themselves to upgrading through screening. The Company has commenced a screening and gold
recovery project, processing the product at its Wonawinta plant. It has confidence the gold from these
sources can be extracted profitably and over a period of ~3 years. Manuka also awaits the outcome of
its forthcoming exploration program to determine as to whether the future for mining any Mt Boppy
extensions will be as an underground or open cast mine;
▪
Silver - Wonawinta silver project, with mine, 84 person mine camp, processing plant and neighbouring
tenements. Previously renowned as the largest primary producer of silver in Australia, the mine hosts
a significant JORC resource7. The Wonawinta processing plant has a nameplate capacity of >850,000
tonnes per year (which the Company now sees expanded to >1.0Mt/yr. The Company has recently
completed a plant and metallurgical recovery optimisation.
There exists a number of highly prospective base metals exploration targets on Manuka’s ~1,150km 2
tenement package within the Cobar Basin.
The Taranaki VTM Iron Sand Project recently released its maiden vanadium resource 8 which ranks it as
one of the largest drilled vanadium projects globally. The Project has a granted mining licence and is in the
lowest quartile of the iron ore production cost curve. The Company awaits the reissuance of its
Environmental Approval before completing its Bankable Feasibility Study.
6 ASX release 29 July 2022
7 ASX release 1 April 2021
8 ASX release 1 March 2023
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
APPENDIX 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Manuka Resources Ltd
ABN
Quarter ended (“current quarter”)
80 611 963 225
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
30 September 2023
Current quarter
$A’000
Year to date
(3 months)
$A’000
6,539
6,539
(a) exploration & evaluation
(4)
(4)
(b) development
(67)
(67)
(c) production
(4,598)
(4,598)
(d) staff costs
(2,480)
(2,480)
(e) administration and corporate costs
(1,247)
(1,247)
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
-
-
1.5
Interest and other costs of finance paid
(356)
(356)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
186
186
1.9
Net cash from / (used in) operating
activities
(2,028)
(2,028)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
(561)
(561)
(d) exploration & evaluation
(282)
(282)
(e) investments
-
-
(f)
-
-
other non-current assets
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
2.2
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
(24)
(24)
2.6
Net cash from / (used in) investing
activities
(866)
(866)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
1,048
1,048
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(60)
(60)
3.5
Proceeds from borrowings
3,938
3,938
3.6
Repayment of borrowings
(2,107)
(2,107)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
(35)
(35)
3.10
Net cash from / (used in) financing
activities
2,783
2,783
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
266
266
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(2,028)
(2,028)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(866)
(866)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
2,783
2,783
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
156
156
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
156
266
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
156
266
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
174
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: 6.1 This is made up of amounts paid to the directors including salary, directors’ fees, consulting fees and
superannuation.
Note: 6.2 This is made up of amounts paid to the directors including consulting fees in respect of exploration activities.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
29,375
28,711
7.1
Loan facilities
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
29,375
28,711
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
Lender
Facility type
TransAsia
Private Capital
Limited
ResCap
Investments
Pty Ltd
Various
Secured Senior
Debt Facility
plus interest
Unsecured
Working
Capital Loan
Equipment
Finance
Short-term
finance
Tennant Metals
Trade Finance
stockpile facility
Variou
Total Facility
664
Rate
Maturity
15,599
15%
30/09/2024
2,000
16%
30/09/2024
935
21%
29/04/2025
1,183
12%
9,657
39%
31/08/2023
3 year trade
finance facility
expiring April
2026
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
8.4
Cash and cash equivalents at quarter end (item 4.6)
156
8.5
Unused finance facilities available at quarter end (item 7.5)
664
8.6
Total available funding (item 8.4 + item 8.5)
815
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
0.35
(2,028)
(282)
(2,310)
Note: if the entity has reported positive relevant outgoings (i.e. a net cash inflow) in item 8.3, answer item 8.7 as
“N/A”. Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
tel +612 7253 2020
www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer:
The Company has recommenced gold production as announced to the ASX on 14
June 2023 and the first cash inflows from gold sales occurred during July 2023. The
Company has increased production over the quarter with a total of 2,117oz of gold
sold (of which 1,239 oz of gold was sold during September 2023). October 2023 gold
sales are estimated to be ~1,100 oz (gold recoveries will be ~1300oz in October
which is highest to date for the screening project). Continued production at this level
will mean that the next quarter will achieve positive operating cashflows.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
At 30 September 2023 the Company has excess finance facilities available and as
noted at 8.8.1 above, the quarter ended 31 December 2023 is expected to achieve
positive operating cashflows with production at current levels. In addition, the
Company had ~$4Million of gold in circuit as at 30 September 2023.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
With the commencement of gold sales in July 2023 and continued gold production at
current levels means that the Company should achieve positive operating cashflows
during the quarter ended 31 December 2023.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
30 October 2023
Authorised by: ...................................................................................
Toni Gilholme – Company Secretary
On behalf of the Board of Directors
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity
that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged
to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in,
and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows
apply to this report. If this quarterly cash flow report