June 2026 Quarter Activities and Cashlfow Reports
Released
Released
Announcement PDF
ASX Announcement
31 July 2026
ASX: MKR
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
June 2026 Quarterly Activities Report
Manuka Resources Limited (ASX: MKR) (Manuka or the Company) is pleased to provide
the following report on its activities for the quarter ended 30 June 2026.
Highlights
Quarter Highlights
Manuka advanced closer to final restart at the Wonawinta Processing Plant, with
refurbishment, commissioning and operational readiness progressing throughout the
quarter.
Upgraded crushing and deslime circuits from South Africa now fabricated and built, with
the first equipment shipments underway.
Continued crushing, haulage and stockpiling of Mt Boppy gold-bearing ore ahead of
processing (>50,000t of material hauled to Wonawinta at 30 July 2026).
Completed initial round of RC resource definition drilling at the Pipeline Ridge Gold
Project. Assay results delivery in progress with expected completion scheduled late
August 2026. Drilling results will be reported when all received.
Camp upgrades, recommissioning, workforce mobilisation and site expansion and
refurbishment continued as Wonawinta transitions from previous care and maintenance
state into operational state.
Successfully completed the final ~US$4.0 million drawdown under the Nebari Natural
Resources Credit Fund II LP senior debt facility.
Post Quarter End
Increased the Wonawinta Probable Ore Reserve1 by 28% to 7.9Mt containing 12.8Moz
of silver, strengthening the Company’s production profile ahead of operations restart.
Staggered delivery to site of the primary and secondary crusher and silver deslime
circuits from South Africa commenced in July.
Manuka remains on track to initially commence gold production during the September
quarter with silver production commencing in October 2026.
Executive Chairman’s Commentary
Dennis Karp, Manuka’s Executive Chairman, commented:
“The June quarter marked a defining period for Manuka, preparing the Wonawinta Processing
Plant for restart of silver and gold production.
During the quarter, we made significant progress with the camp and plant refurbishment,
preparing for operational readiness. We continued the crushing, screening and hauling of Mt
Boppy gold ores as we build stockpiles at Wonawinta ahead of processing and completed the
final drawdown under our Nebari funding facility.
1
ASX Announcement 13 July 2026; Update Ore Reserve – Wonawinta Silver Mine
Page | 2
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Following quarter end, we achieved several important milestones.
We increased the Wonawinta Ore Reserve by 28% to 7.9Mt containing 12.8 million ounces of
silver, commenced shipping the upgraded crushing and deslime equipment from South Africa
and completed the first round of RC resource definition drilling at our Pipeline Ridge Gold Project
situated on EL5842 (drill results to be reported once all received).
Recent equipment delivery delays have pushed out our recommissioning of the Wonawinta
plant and we now expect to commence sustained precious metals production, initially from Mt
Boppy gold ore, around mid-August before transitioning to silver production in October.
Achieving these milestones will mark Manuka’s transformation from developer to producer
enabling the Company to commence sustainable cashflow generation from its Cobar Basin
operations.”
Operations – Wonawinta Processing Plant
The Wonawinta Processing Plant is a fully permitted 1.0Mtpa conventional carbon in leach
circuit with a dual stream elution circuit capable of producing a silver and gold product stream.
The plant will initially process gold ore hauled from the Company’s nearby Mt Boppy Gold
Project before incorporating silver production from the Wonawinta Silver Project positioning
Manuka to become Australia’s largest primary silver producer.
The June quarter was characterised by continued execution of Manuka’s production restart
strategy as the Company progressed the processing plant through what is close to final stages
of refurbishment, commissioning and operational readiness.
During the quarter, the Company completed the final US$4.0 million drawdown under its senior
secured debt facility with Nebari Natural Resources Credit Fund II LP (Nebari), securing the
funding required to restart the plant and transition into production.
Wonawinta plant refurbishment and commissioning activities continued under the supervision
of the company’s operational readiness team with substantial progress achieved across the
major processing circuits. Operational readiness also advanced through camp upgrades and
recommissioning, workforce mobilisation, site expansion, refurbishment and plant restart
preparation.
Mining and site activities progressed during the quarter, supported by Macmahon Contractors
Pty Ltd, one of Australia’s leading mining contractors, under a separate package of pre-mining
site and open pit activities. In parallel, crushing, haulage and stockpiling of Mt Boppy gold-
bearing ore at Wonawinta continued in readiness for plant start-up.
Construction of the upgraded front-end crushing and deslime circuits by Bond Equipment (South
Africa) continued during the quarter, with fabrication, factory testing, logistics planning and
scheduling and commencements of shipments to Australia. Once commissioned, the deslime
circuit is expected to improve plant throughput and metallurgical performance through the
removal of clay-rich material ahead of milling.
Page | 3
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Post Quarter End
Since the end of the June quarter, Manuka achieved several important milestones as it
transitions to gold and silver production.
On 13 July 2026, the Company announced a 28% increase in the Wonawinta Probable Ore
Reserve to 7.9 million tonnes containing 12.8 million ounces of silver, strengthening
confidence in the production plan while highlighting the conversion potential of the broader
51Moz Mineral Resource2.
Following the reporting period, the first consignments of the crushing and deslime circuits were
shipped to Australia in July. Installation in the September quarter will be completed as part of
the final plant integration and upgrade programme.
The Company remains on track to commence sustained gold production from Mt Boppy ore
mid-August 2026, followed by silver production in October 2026, completing Manuka’s transition
to commercial precious metals production.
Mt Boppy Gold Project
Mt Boppy remains a key cornerstone of Manuka’s production strategy, providing the initial
source of gold ore feed for plant recommissioning, start-up and early production at the
Wonawinta Processing Plant.
During the quarter, crushing, screening and haulage activities continued, with gold-bearing
material trucked to Wonawinta to establish stockpiles ahead of plant start-up. These stockpiles
are expected to initially support sustained precious metals production from August 2026,
following completion of the remaining plant integration works.
A second infill phase of sonic drilling was completed during Q1 2026 on the Mt Boppy Main
Waste Dump. During the quarter fire assay and cyanide bottle roll assay results from this drilling
have continued to be received (Table 1).
Table 1: Mt Boppy Main Waste Dump Sonic Drilling as at 30 June 2026
Drilling Type No. holes 1m Samples
Drill hole Head
grade FA received
Drill hole Bottle Roll
Assay Received
Drill holes
Outstanding
Sonic 49 445 31 30 19
Assay results will be reported when all assays have been received and validated.
On receipt of final assays during Q3 2026, the Mt Boppy waste dump block model will be revised
and the production plan (which involves a combination of screening only and crushing &
screening certain waste lithologies) updated.
As production ramps up, Mt Boppy ores are expected to provide early operating cashflow while
positioning the Company for the transition to primary silver production at Wonawinta.
2 ASX Announcement 13 July 2026: Update Ore Reserve – Wonawinta Silver Mine
Page | 4
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
During the quarter, analysis and interpretation of the Mt Boppy Southern extension exploration
reverse circulation (RC) and diamond (DD) drilling programme continued, mostly focusing on
completion of pXRF analyses of the photon assay sample pulps (Table 2).
Table 2: Mt Boppy Southern Extension RC and DD Exploration Drilling 30 June 2026
Drilling Type
No.
holes
1m
Samples
Photon Assay Received Assays Outstanding pXRF Analyses
Mt Boppy RC/DD 3 1,686 1,686 - 1,686
These drilling assay results have been reported to the ASX 28 April 20263
The Company
continues to assess near term opportunities to optimise and expand the Mt Boppy gold system
through targeted exploration and resource growth initiatives, supporting Manuka’s broader
strategy of establishing a long-life, multi-source precious metals business across the Cobar
Basin.
Pipeline Ridge Gold Project
An initial phase of RC resource definition drilling at the Pipeline Ridge Gold Project was
completed during the quarter, targeting shallow oxide gold mineralisation suitable for open pit
extraction approximately 28km south of the Mt Boppy Gold Mine within Manuka’s broader Cobar
Basin production hub.
The programme comprised 3,133 metres of RC drilling testing a zone of approximately 500m to
depths of around 60 metres (Table 3), and designed to support a maiden Mineral Resource
Estimate during 2026. The current exploration target comprises 187,000 to 365,000 tonnes
grading between 1.1g/t and 1.5g/t gold4 The exploration target was derived from the analysis
of historical RC (6079m) and diamond drilling (6590m) on the property, and a preliminary
Inverse Distance Squared block model erected over the gold mineralised zone mentioned
above. The tonnage and grade range estimates reflect material between 0.6 and 0.8 g/t Au cut
off grades The potential quantity and grade of this exploration target is still conceptual, and
historic exploration was insufficient to define a Mineral Resource. It is still uncertain until all
results are received from the current drilling programme that further exploration will result in a
mineral resource estimate.
Note the potential range of quantity and grade stated above is conceptual, and that exploration to date is
insufficient to define a Mineral Resource, and that it is uncertain further exploration will result in one.
Table 3: Pipeline Ridge RC Resource Definition Drilling 30 June 2026
Drilling Type
No.
holes
1m Samples Fire Assay Received Assays Outstanding pXRF Analyses
Pipeline Ridge RC 56 3,133 752 2,381 3,183
Assay results will be reported once all assays have been received and validated.
The RC drilling gold fire assay results are in progress (2,381 outstanding) and are expected to
be completed by late August 2026 and will underpin geological modelling and initial mineral
resource estimation activities.
3 ASX Announcement 28 April 2026 and 11 May 2026: Mt Boppy Gold Project Exploration Update
4
ASX Announcement 28 April 2026 and 11 May 2026: Mt Boppy Gold Project Exploration Update (refer Pipeline Ridge Gold
Project – Resource Definition Drilling)
Page | 5
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Pipeline Ridge represents a compelling near-term growth opportunity, with the potential to
provide an additional source of gold ore feed for the Wonawinta Processing Plant, subject to
completing regulatory approvals.
A successful resource outcome at Pipeline Ridge would further strengthen Manuka’s strategy
of developing a multi-source precious metals production hub across the Cobar Basin, increasing
production flexibility, extending mine life and enhancing long-term cashflow potential.
Exploration & Future Growth Potential
While the Company’s immediate focus is the successful ramp-up of Wonawinta gold and silver
production, Manuka continues to advance targeted exploration programmes aimed at extending
mine life and maximising utilisation of the 1Mtpa Wonawinta Processing Plant.
During the quarter, geological evaluation continued across the broader Mt Boppy Gold Project,
with recent structural drilling providing further insights into the controls on gold mineralisation.
This work has refined the Company’s geological model and will support future drill targeting,
including shallow satellite deposits and strike extensions capable of supplementing future plant
feed.
The Pipeline Ridge Project has progressed with the completion of an initial shallow (~60m) open
pit delineation drilling programme. Future drilling has been planned and will be undertaken
subject to results of the Manuka initial phase of RC drilling.
Beyond Mt Boppy and Pipeline Ridge, Manuka maintains an extensive portfolio of highly
prospective gold and silver tenements across the Cobar Basin. Exploration remains focused on
identifying additional deposits within economic haulage distance of Wonawinta, supporting the
Company’s strategy of building a long-life, multi-source precious metals production hub.
As Manuka transitions into production, exploration will remain disciplined and value-driven,
prioritising opportunities capable of delivering additional ore feed, extending mine life and
increasing long-term production and cashflow.
Taranaki VTM Project
The Taranaki VTM Project in New Zealand remains a significant long-term strategic asset within
Manuka’s portfolio.
During the quarter, the Company continued to preserve the value of the project while
maintaining a disciplined approach to capital allocation. Activities included reviewing the Fast-
track Approvals application process and outcomes along with the EPA’s ongoing cost recovery
claims for the expert panel hearing.
The Company will continue to monitor developments in New Zealand’s regulatory environment
and evaluate opportunities to progress the Taranaki iron sands project, and its critical minerals
potential, as permitting pathways, market conditions and regulatory opportunities evolve, while
preserving the project’s long-term strategic value for shareholders.
Corporate
During the quarter, Manuka completed the final US$4 million drawdown under its senior secured
debt facility with Nebari, securing the funding required to restart the Wonawinta Processing
Plant and transition into production.
Page | 6
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
As part of this drawdown, Manuka issued 8,232,731 warrants to Nebari expiring on 26 June
2030. As at 30 June 2026, Nebari holds a total of 44,656,343 warrants.
The Company’s operational readiness capability continued to strengthen throughout the
quarter, with recruitment across operations, maintenance and technical functions building out
the operation team across all disciplines.
Manuka also continued to progress its broader corporate strategy, maintaining a disciplined
focus on operational execution, financial stewardship and creating long-term shareholder value
as it moves into sustained production and cashflow generation.
Financial Position
At 30 June 2026, the Company held cash and cash equivalents of A$7.8 million.
During the quarter, expenditure was primarily directed towards refurbishment and
commissioning of the Wonawinta Processing Plant, workforce mobilisation, infrastructure
upgrades and production readiness activities. Capital investment also continued in the
manufacture of upgraded crushing and deslime circuits, supporting the Company’s strategy of
improving long-term plant performance and operating efficiency.
With the completion of the final Nebari funding drawdown during the quarter, Manuka has
entered the next phase of its development as it transitions from project restart to operating
cashflow generation.
Cashflow and Hedging
The Company did not have any open hedge contracts as at 30 June 2026.
Total borrowings as at 30 June 2026 were A$52.5 million. Unused facilities available at Quarter
end were A$5.0 million and the cash balance was A$7.8 million.
In accordance with ASX Listing Rule 5.3.5, during the quarter, the Company made cash
payments of $0.293 million to related parties and their associates (refer items 6.1 and 6.2 of the
Appendix 5B). This was the aggregate amount paid to the directors including salary, directors’
fees, consulting fees and superannuation.
Mining Development Activities
In accordance with ASX Listing Rule 5.3.1 cash outflows for the quarter in relation to exploration
development activities were $1.338 million (refer items 1.2(a) and 2.1(d) of the Appendix 5B).
The cost related to salaries and wages for geology, as well as licencing fees, metallurgical test
work and assays.
Mining Production Activities
In accordance with ASX Listing Rule 5.3.2, cash outflows for the quarter relating to mining
production and development activities focused on detailed planning, execution and readiness
activities to support the transition from Care & Maintenance into operations.
Mining Tenements
In accordance with ASX Listing Rule 5.3.3, the following information is provided for the quarter
ended 30 June 2026.
Page | 7
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Wonawinta Silver Project tenements are located approximately 90km to the south of Cobar,
NSW, and comprise one (1) granted mining lease and seven (7) granted exploration licenses as
below, plus processing plant and associated infrastructure.
Tenement Percentage held / earning Change during Quarter
ML1659 100% -
EL6482 100% -
EL7345 100% -
EL6155 100% -
EL6302 100% -
EL7515 100% -
EL6623 100% -
EL8498 100% -
Mt Boppy Gold Project tenements are located approximately 45km east of Cobar, NSW,
adjacent to the Barrier Highway. The Project comprises four gold leases, two mining leases, one
mining purpose lease and one exploration licence which encompasses the MLs and extends the
project area to the south.
Tenement Percentage held / earning Change during Quarter
GL3255 100% -
GL5836 100% -
GL5848 100% -
GL5898 100% -
ML311 100% -
ML1681 100% -
MPL240 100% -
EL5842 100% -
Taranaki VTM Iron Sand Project tenements are located offshore in the South Taranaki Bight of
the North Island, New Zealand. Tenements comprise one 243km2
granted mineral mining permit
and one 635km2
granted mineral exploration permit.
Tenement Percentage held / earning Change during Quarter
MMP55581 100% -
MEP54068 100% -
There were no tenements disposed of and no farm-in or farm-out agreements entered into during
the quarter.
Page | 8
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Compliance Statements
The information in this announcement that relates to previously reported Exploration Results, Exploration
Targets, Mineral Resources, Ore Reserves, Production Targets and Financial Forecasts is extracted from
the Company’s ASX announcements and are available to view on the Company’s website. The Company
confirms that, other than mining depletion, it is not aware of any new information or data that materially
affects the information included in the original announcements and, in the case of estimates of Mineral
Resources and Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant announcement continue to apply and have not materially changes. The
Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially altered.
Important Information
This report includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other
similar expressions are intended to identify forward-looking statements. Such statements involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company, and which may cause actual results, performance or achievements to differ
materially from those expressed or implied by such statements. Forward-looking statements are provided
as a general guide only and should not be relied on as an indication or guarantee of future performance.
Given these uncertainties, recipients are cautioned to not place undue reliance on any forward-looking
statement. Subject to any continuing obligations under applicable law, the Company disclaims any
obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in
this report to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based. No Limited Party
or any other person makes any representation or gives any assurance or guarantee that the occurrence
of the events expressed or implied in any forward-looking statements in the report will occur.
For further information contact:
Dennis Karp
Executive Chairman
Tel. 02 7253 2020
admin@manukaresources.com.au
Page | 9
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Manuka Resources Limited
ABN Quarter ended (“current quarter”)
80 611 963 225 30 June 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(165) (869)
(a) exploration & evaluation
(b) development - (145)
(c) production (4,068) (8,486)
(d) staff costs (1,673) (3,944)
(e) administration and corporate costs (1,351) (8,198)
1.3 Dividends received (see note 3) -
1.4 Interest received -
1.5 Interest and other costs of finance paid (2,271) (5,912)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - 153
1.9 Net cash from / (used in) operating
activities
(9,528) (27,401)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (2,175) (8,511)
(d) exploration & evaluation (1,173) (1,697)
(e) investments -
(f) other non-current assets - (1,117)
Page | 10
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - (32)
2.6 Net cash from / (used in) investing
activities
(3,348) (11,357)
3. Cash flows from financing activities
5,971 38,368
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
-
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(216) (1,859)
3.5 Proceeds from borrowings 5,684 53,751
3.6 Repayment of borrowings (537) (44,483)
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) (230) (218)
3.10 Net cash from / (used in) financing
activities
10,672 45,559
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
9,974 969
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(9,528) (27,401)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(3,348) (11,357)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
10,672 45,559
Page | 11
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
7,770 7,770
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 7,770 7,770
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
7,770 7,770
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
293
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Page | 12
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities 57,457 52,457
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities 57,457 52,457
7.5 Unused financing facilities available at quarter end
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
Lender Facility Type Total Facility Rate Maturity
Nebari Secured Senior
Debt Facility
US$31.4m 12.5% 31/03/2030
Various Equipment
Finance
A$2.6m 12.0% 12/06/2030
Tennant Metals Second ranking
working capital
US$7.0m 14.0% 30/11/2027
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (9,528)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(1,173)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (10,701)
8.4 Cash and cash equivalents at quarter end (item 4.6) 7,770
8.5 Unused finance facilities available at quarter end (item 7.5) 5,072
8.6 Total available funding (item 8.4 + item 8.5) 12,842
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
1.20
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: The entity does not expect that it will continue to have the current level of net
operating cash outflows as it is completing the installation of new plant to
commence operations.
Page | 13
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: The entity will take additional steps to secure contingency finance in case it
becomes required. Additional finance could be in the form of debt or equity.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: The entity does expect to continue its operations and meet its business objectives.
During the next quarter operations will commence and inflows from the sale of gold
will begin.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
31 July 2026
Date: ...................................................................................
The Board of Manuka Resources Limited
Authorised by: ...................................................................................
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activit