December 2024 Quarter Activities and Cash Flow Reports
Released
Released
Announcement PDF
ASX Announcement
31 January 2025
ASX: MKR
December 2024 Quarterly Activities Report
Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide the
following report on its activities during the quarter ending 31 December 2024.
Highlights
•
Maiden Reserve released for the Wonawinta Silver Mine (“Wonawinta”):
o 4.8Mt at 53.8g/t Ag containing 8.4Moz of silver1.
o Ore Reserve is based solely on shallow (<40m deep) oxide material.
o Wonawinta Resource comprises 38.3Mt at 41.3g/t Ag for 51Moz of silver2.
•
Wonawinta is the only primary silver Reserve in Australia with all mining
approvals current and a process plant fully constructed.
•
Extension granted for the repayment of existing debt facility with Hong Kong
based lender. Facility now due on 31 May 2025. Refinance process ongoing.
•
Successful funding initiatives raising A$3.4m completed substantially
strengthening the Company’s balance sheet. A$1.4m of these funds will be
directed to Trans-Tasman Resources Ltd’s (“TTR”) Fast Track Application in New
Zealand which TTR will lodge during this quarter.
•
Progression of metallurgical test work required to support the installation of a
gold processing facility at Manuka’s 100% owned Mt Boppy gold project (“Mt
Boppy”).
•
New Zealand’s ‘one-stop-shop’ Fast Track Approvals Act 2024 (“Fast Track
Act”) had its third and final reading on 17 December 2024, was voted into law
and on 23 December 2024 given Royal Assent. TTR’s Taranaki VTM Project in
the South Taranaki Bight (STB) is one of the major projects included in the
schedule of projects for consideration under the Act to be considered for approval
by an expert panel after lodgement of its application this quarter.
•
The 11 mining projects listed on Schedule 2 of the Act, including TTR’s
Taranaki VTM Project, will support the Government’s aim to double the
value of mineral exports to $3 billion by 2035. NZ Prime Minister Christopher
Luxton in his 23 January 2025 State of the Nation Speech3 stated “mining needs
to play a much bigger role in the New Zealand economy”.
1
ASX release 29 October 2024.
ASX release 1 April 2021.
3
https://www.beehive.govt.nz/speech/state-nation-2025
2
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Post Quarter End
The New Zealand government finalised a Critical Minerals List to identify minerals essential to the
economy and technological needs and released this list today 31 January 2025. Both titanium and
vanadium are included in the critical minerals list, which is a further positive for TTR’s Taranaki VTM
Project.
New Zealand Prime Minister Christopher Luxton’s State of the Nation 2025 speech4 on 23 January
2025 highlighted the new Fast Track legislation and the importance of mining in the New Zealand
economy moving forward including the following:
“Fast Track will supercharge economic growth, enabling major investments and growth in energy,
transport, aquaculture, and a range of other sectors – but we can go further.”
“In regions like Taranaki and the West Coast there are big economic opportunities – higher incomes,
support for local business and families, and more investment in local infrastructure.”
“The minerals sector will also be critical for our climate transition – EVs, solar panels, and data
centres aren’t made out of thin air.”
These encouraging sentiments were followed up by the NZ Resources minister Shane Jones in a
speech5 he delivered at OceanaGold’s Waihi mine today (31 January 2025), signalling a new
direction for the growth of the NZ minerals sector and the resources friendly policy of his government
and announced the finalised NZ Critical6 Mineral list and the country’s Mineral7 Strategy.
“The Minerals Strategy for New Zealand adopts a strategic lens out to 2040, focusing our approach
to the development of our minerals estate with a delivery roadmap to get us there. This is a holistic
picture of minerals production from the earth, from reprocessing waste material, and from potential
recycling and recovery.”
“We have updated the goal of doubling our exports to $3 billion by 2035 from the previous goal of
$2 billion. Statistics NZ reports that mineral exports for the financial year ending June 2023 totalled
$1.46 billion and our submitters were clear – we needed a more ambitious goal.”
“This Government is taking an active, deliberate and co-ordinated approach to harnessing the
potential of our natural resources to take us from 'open for business' to 'doing business'.”
4
https://www.beehive.govt.nz/speech/state-nation-2025
5
https://www.beehive.govt.nz/speech/new-direction-minerals-sector-grow-economy
6
https://www.beehive.govt.nz/sites/default/files/202501/202501%20New%20Zealand%27s%20Critical%20Minerals%20List.pdf
7
https://www.beehive.govt.nz/sites/default/files/202501/202501%20A%20Minerals%20Strategy%20for%20New%20Zealand%20to
%202040.pdf
Page | 2
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Figure 1 Location of Resources Development Projects in New Zealand. Source: “A Minerals Strategy
for New Zealand to 2040” - January 2025
Page | 3
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Dennis Karp, Manuka’s Executive Chairman, commented:
“On 23 December the New Zealand government passed the Fast Track Approvals Act 2024 (the
“Fast Track Act”) into law. The Fast Track Act provides a streamlined decision process to
facilitate the delivery of natural resource and infrastructure development projects with significant
regional or national benefits. TTR (Manuka’s wholly owned subsidiary), is the 100% owner of
the Taranaki VTM Project on which over NZ$85m has been expended on resource
development, mine planning, process design, metallurgical test work, world expert
environmental planning, and the completion of a robust pre-feasibility study (PFS). The project
is listed in Schedule 2 of the Fast Track Act to be considered by an expert panel for final
development approvals. The passing of the Fast Track Act should prove to be of enormous
significance to the Company and we anticipate lodging our application to the EPA for the
granting of Marine and Discharge Consents in the very near future. It is important to note that
TTR already has a granted Mining Permit.
Manuka’s Maiden Silver Ore Reserve and the preparation of an Implementation Plan for
Wonawinta represents a major milestone for the Company and supports a potential restarting
of silver mining and processing operations. Our process plant at Wonawinta has been kept in
excellent condition and on active care & maintenance since the processing of gold from
stockpiles hauled from Mt Boppy, ceased in February 2024 and therefore stands ready to come
back online at short notice.
Manuka continues to progress with the evaluation of installing of a processing plant at its 100%
owned Mt Boppy gold project, with the aim of restarting gold production. During the quarter
metallurgical testwork was undertaken on samples collected from the historic tailings facility.
Background
Manuka Resources Limited (“Manuka” or the “Company”) is an ASX-listed producer, developer
and explorer with a 100% interest in two fully permitted precious metal mines located in the
Cobar Basin NSW as well as a world-class VTM iron sands resource located in New Zealand.
Operations at both Mt Boppy and Wonawinta continued in a state of care and maintenance,
which had initially been introduced during the March 2024 quarter.
Following the passage of the NZ Fast Track Act, TTR is now targeting the lodgement of its
application for its Taranaki VTM iron sands project under the Fast Track Act this quarter. In
parallel, the Company is also pursuing the return to profitable gold and silver production from
its NSW assets and the generation of free cash flow to self-fund further project development
and exploration.
Mt Boppy Gold Mine
The initial ~3.5-year Mt Boppy mine plan8 focuses on reprocessing the rock dumps and tailings.
During the quarter, the Company continued optimising its proposed mine plan and undertook
additional metallurgical testwork on the tailings samples to refine process flow sheet design.
The establishment of a processing facility at Mt Boppy and commencement of production
remains contingent on ongoing metallurgical testwork results and project finance being secured
in conjunction with the ongoing process to refinance the existing senior debt facility. The
Company is currently undertaking an independent technical review of the Project to support the
refinancing process.
8 ASX release 30 September 2024
Page | 4
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Wonawinta Silver Mine
Previously Australia’s largest primary silver mine, Wonawinta produced approximately 3Moz
silver from 2012 to 2014. Most recently, the process plant at Wonawinta has been used to
process gold ores from the Mt Boppy Mine located 150km to the north between 2020 and 2023.
Between October 2022 and February 2023, a trial campaign of silver production from historic
oxide stockpiles on the ROM at Wonawinta was undertaken by the Company. During the trial
period, Manuka completed a series of modifications and innovations to the Wonawinta
processing facility including the introduction of a de-slime circuit to remove deleterious fine clays
from the ore and increase feed grade into the CIL circuit.
Metallurgical test work, confirmed by production data, saw an uplift in silver feed grades to the
leach circuit by up to 100%. Higher grades and lower clays increased silver loadings onto
carbon. The improvements and innovations achieved were material leading to an increase in
capacity to >1.0Mtpa of material through the plant (from nameplate capacity of 850Ktpa).
The Company has been making steady progress towards the restart of its Wonawinta silver
project against a backdrop of positive movements in the price of silver. During the quarter, the
Company the release of a Maiden Silver Reserve comprising 4.8Mt at 53.8g/t silver containing
8.4Moz (Table 1) and an associated Implementation Plan9.
The Ore Reserve represents only 13% of the defined Mineral Resource of 38.3Mt at 41.3g/t Ag
for 51Moz of silver10. Further infill drilling between the proposed open pits is anticipated to
increase Resource confidence and allow for its incorporation into the Reserve based mine plan.
Table 1: Wonawinta Silver Project Ore Reserve
Classification
Mt
g/t Ag
Moz
Proved
0.8
50.8
1.3
Probable
4.1
54.3
7.1
Total
4.8
53.8
8.4
Note: Tonnes and Grade are rounded. Discrepancies in calculated Contained Metal is due to rounding.
The Wonawinta plant, having been in production as recently as January 2024 and on an active
care and maintenance program since, stands ready for a rapid restart of production subject to
the undertaking of limited restart maintenance.
Wonawinta is the only primary silver Reserve in Australia with all mining approvals current and
a process plant fully constructed. The highly strategic mine is within trucking distance of
significant undeveloped deposits and current operations within the prolific Cobar basin.
Additionally, the Wonawinta deposit, a predominantly carbonate-hosted Ag-Pb-Zn deposit with
similarities to the Mississippian Valley Type (“MVT”), is prospective down dip for base metal lead
and zinc mineralization as evidenced by proof-of-concept drilling completed in 202111.
9 ASX release 29 October 2024
10
ASX release 1 April 2021
11 ASX release 1 June 2021
Page | 5
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Taranaki VTM Iron Sands Project
Manuka holds a 100% interest in the Taranaki VTM Iron Sands Project via its wholly owned
subsidiary TTR. Located offshore in the STB, within New Zealand’s Exclusive Economic Zone
(“EEZ”), the project comprises a 3.2Bt vanadiferous titanomagnetite (“VTM”) iron ore resource12
at 10.17% Fe2O3, 0.05% V2O5 (containing 1.6Mt V2O5) and 1.03% TiO2 (Table 2), ranking it as
one of the largest drilled vanadium projects globally. Indicated Resources comprise 65.7% of
the total Resources with the balance being Inferred.
Table 2: Taranaki VTM Iron Sands Project Mineral Resource
Resource
Bt
Fe2O3 (%)
TiO2 (%)
V2O5 (%)
Indicated
2.1
10.45
1.06
0.05
Inferred
1.1
9.64
0.99
0.04
Total
3.2
10.17
1.03
0.05
TTR has granted mineral mining permit MMP55581 within the EEZ containing 1.88Bt VTM
resource where the current PFS mine plan can deliver production of 5Mt export concentrates a
year grading 56-57%Fe, 0.5%V2O5 and 8.5%TiO2. TTR’s adjoining mineral exploration permit,
MEP54068 inside the 12Nm limit within the Coastal Management Area (“CMA”), contains a
reported additional 1.29Bt VTM iron sands resource.
On 23 December the New Zealand government passed the Fast Track Approvals Act 2024 (the
“Fast Track Act”) into law. TTR’s Taranaki VTM Project is listed in Schedule 2 of the Fast Track
Act to be considered by an expert panel for final approvals to develop. Schedule 2 projects,
including TTR’s, are considered to meet the Fast Track Act’s purpose including being projects
of regional or national significance.
From 7 February 2025, TTR will be able to make application to the EPA to have its VTM project’s
Marine and Discharge environmental approvals consented. TTR is now preparing to lodge an
application under the Fast Track Act for consideration by a panel whose members have relevant
knowledge and expertise in mining projects, to consider the reissuance of the Marine and
Discharge Consents and apply any relevant conditions. This expert panel assessment process
will be undertaken in early 2025.
On 31 January 2025, the New Zealand government released its final Critical Minerals list.
Prepared by international consultants Wood Mackenzie the list includes both vanadium and
titanium.
The Critical Minerals list, alongside the Minerals Strategy for New Zealand 2040, also released
on 31 January 2025, and the GNS Report on the country’s potential economic mineral deposits,
released on 29 August 2024, all include offshore Taranaki VTM deposits containing vanadium
and titanium in the STB controlled 100% by TTR. The MBIE reports provide the government
with insight and facts as to the potential for the development of these mineral resources in New
Zealand.
The New Zealand government has identified TTR’s world-class vanadium rich iron sands project
as one of national significance that has the ability to contribute to New Zealand’s economy and
export earnings and to the government’s resource objective of doubling the value of New
Zealand’s mineral exports to $3 billion by 2035.
12 ASX release 1 March 2023
Page | 6
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Exploration Activities
The Company continued surface exploration activities during the quarter, with the focus on the
Mt Boppy south area on EL 5842 (Figure 2).
Figure 2: Mt Boppy South exploration
The field work involved establishing a 200m line spacing and 100m sample spacing grid
straddling the NW-SE terrane boundary between the Baledmund Formation / Florida volcanics
and the Girilambone Formation. The boundary is marked by structural deformation related to
thrusting and accompanying shearing. Small historic shafts (e.g. The Priests, Canbelego Peak,
Prendergast and Mouramba) exploited Cu (Pb-Zn) mineralisation. The soil and auger sampling
orientation programme yielded anomalous Cu-Pb-Zn pXRF values (Figure 2). This phase of
work will be followed up during Q1 2025 with infill sampling on a 50 x 50m grid spacing.
Mining Development Activities
In accordance with ASX Listing Rule 5.3.1 cash outflows for the quarter in relation to exploration
development activities were $0.336 million (refer items 1.2(a) and 2.1(d) of the Appendix 5B).
The cost related to salaries and wages for geology, as well as licencing fees, metallurgical test
work and assays.
Mining Production Activities
In accordance with ASX Listing Rule 5.3.2 cash outflows for the quarter in relation to mining
production and development activities were $0.090 million (refer Item 1.2(b) and 1.2(c) of the
Appendix 5B) and comprised the following:
•
Development
($0.023) million
•
Crushing contractors
$0.077 million
•
Processing
$0.035 million
Page | 7
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Cashflow and Hedging
The Company did not have any open hedge contracts as at 31 December 2024.
During the quarter, the Company completed two separate capital raisings:
•
on 29 November 2024, A$1.0 million via the issue of Convertible Notes with a
conversion price of 6.0c, a 70% premium to the 28 November closing price of 3.5c a
share; and
•
on 17 December 2024, A$2.4 million via the issue of Convertible Notes with a
conversion price 6.0c, a 100% premium to the 16 December closing price of 3.0 cents
a share.
The principal amount outstanding at Quarter end to the Company’s senior secured lender,
TransAsia Private Capital (TA) was US$8.0 million and during the quarter the Company
negotiated an extension of the facility, and this amount is due on 31 May 2025.
Total borrowings as at 31 December 2024 were A$36.84 million. Unused facilities available at
Quarter end were A$1.74 million and the cash balance was $2.038 million.
In accordance with ASX Listing Rule 5.3.5, during the quarter, the Company made cash
payments of $0.234 million to related parties and their associates (refer items 6.1 and 6.2 of the
Appendix 5B). This was the aggregate amount paid to the directors including salary, directors’
fees, consulting fees and superannuation.
Annual General Meeting
The Company held its Annual General Meeting on 27 November 2024, with all resolutions being
successfully passed on a poll.
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
Tel. 02 7253 2020
Media Contact
Ben Henri
M+C Partners
Tel. 0473 246 040
Page | 8
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Mining Tenements
In accordance with ASX Listing Rule 5.3.3, the following information is provided for the
quarter ended 31 December 2024.
Wonawinta Silver Project tenements are located approximately 90km to the south of
Cobar, NSW, and comprise one (1) granted mining lease and seven (7) granted
exploration licenses as below, plus processing plant and associated infrastructure.
Tenement
ML1659
EL6482
EL7345
EL6155
EL6302
EL7515
EL6623
EL8498
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Mt Boppy Gold Project tenements are located approximately 45km east of Cobar,
NSW, adjacent to the Barrier Highway. The Project comprises four gold leases, two
mining leases, one mining purpose lease and one exploration licence which
encompasses the MLs and extends the project area to the south.
Tenement
GL3255
GL5836
GL5848
GL5898
ML311
ML1681
MPL240
EL5842
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Taranaki VTM Iron Sand Project tenements are located offshore in the South Taranaki
Bight of the North Island, New Zealand. Tenements acquired as a result of the acquisition
of TTR (ASX 11 November 2022) comprise one granted mining permit and one granted
exploration permit.
Tenement
MMP55581
MEP54068
Percentage held / earning
100%
100%
Change during Quarter
-
There were no tenements disposed of and no farm-in or farm-out agreements entered into during
the quarter.
Page | 9
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
About Manuka
Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration company with
key gold and silver assets located in the Cobar Basin, central west New South Wales and
offshore vanadium bearing iron sands in the South Taranaki Bight of New Zealand.
The Mt Boppy Gold Mine (Cobar Basin, NSW)
The Mt Boppy gold mine is located 45 km east of Cobar, in the Central West region of New
South Wales. The current Mt Boppy Mineral Resource13 comprises a mix of oxidised and
transitional/fresh in-ground mineralisation, mineralised rock dumps and mineralised tailings.
The Company has to date processed its ROM stockpiles product through the Wonawinta
metallurgical plant. Manuka are currently pursuing a strategy of establishing a fit-for-purpose,
on-site crush-screen-mill-float/leach-facility to enhance the economics of the Mt. Boppy Mine
and the value of near-mine prospects. The Mt Boppy site includes a 48-person mine camp and
is fully permitted for the proposed processing plant and on-site production.
Mt Boppy Gold mine
The Wonawinta Silver Mine (Cobar Basin, NSW)
Previously Australia’s largest primary silver producer, Wonawinta produced approximately 3
million ounces of silver during 2012-2013, and an additional 500,000oz of silver in 2022. The
mine hosts a significant Resource14 - including stockpiles and shallow oxide material, The
Wonawinta processing plant has a nameplate capacity of approximately 850,000 tpa but was
operated at an annualised 1Mtpa during 2022. The Company is reviewing the potential of
recommencing operations at Wonawinta, taking advantage of the strengthening silver price
environment.
13 ASX release 16 April 2024
14 ASX release 1 April 2021
Page | 10
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Wonawinta Silver Mine
The Taranaki VTM Project (South Taranaki Bight, New Zealand)
Manuka’s wholly owned subsidiary, TTR, is the 100% owner of the Taranaki VTM (vanadium
titanomagnetite) Iron Sands Project. The Taranaki VTM Project mineral resource statement was
released on ASX on 1 March 2023.
The Taranaki VTM Project is located 22km to 36km offshore in New Zealand’s Exclusive
Economic Zone (EEZ), outside the 12 nautical mile limit from the shoreline, in waters ranging
between 20 to 50 metres depth. The prefeasibility study (PFS) is based on a mining plan15 which
can deliver production of 5Mt export concentrates a year grading 56-57%Fe, 0.5%V2O5 and
8.5%TiO2. On granting of final government approvals (regranting of Marine and Discharge
Consents) the Company will complete its Bankable Feasibility Study (BFS) on the Project.
Management anticipates the Project will sit in the lowest quartile of the iron ore production cost
curve.
15Manuka Resources Limited ASX Release “Execution of Binding Terms Sheet for Trans-Tasman Resources Limited (TTR)” 1
August 2022
Page | 11
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Taranaki VTM Project, South Taranaki Bight, New Zealand
Compliance Statements
The information in this announcement that relates to previously reported Exploration Results, Exploration
Targets, Mineral Resources, Ore Reserves, Production Targets and Financial Forecasts is extracted from
the Company’s ASX announcements and are available to view on the Company’s website. The Company
confirms that, other than mining depletion, it is not aware of any new information or data that materially
affects the information included in the original announcements and, in the case of estimates of Mineral
Resources and Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant announcement continue to apply and have not materially changes. The
Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially altered.
Important Information
This report includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other
similar expressions are intended to identify forward-looking statements. Such statements involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company, and which may cause actual results, performance or achievements to differ
materially from those expressed or implied by such statements. Forward-looking statements are provided
as a general guide only and should not be relied on as an indication or guarantee of future performance.
Given these uncertainties, recipients are cautioned to not place undue reliance on any forward-looking
statement. Subject to any continuing obligations under applicable law, the Company disclaims any
obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in
this report to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based. No Limited Party
or any other person makes any representation or gives any assurance or guarantee that the occurrence
of the events expressed or implied in any forward-looking statements in the report will occur.
Page | 12
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
APPENDIX 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Manuka Resources Ltd
ABN
Quarter ended (“current quarter”)
80 611 963 225
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 December 2024
Current quarter
$A’000
Year to date
(6 months)
$A’000
4
4
(221)
(441)
(b) development
23
16
(c) production
(112)
(482)
(d) staff costs
(802)
(1,427)
(4,045)
(3,078)
(a) exploration & evaluation
(e) administration and corporate costs
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
-
-
1.5
Interest and other costs of finance paid
3,113
1,789
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
304
347
1.9
Net cash from / (used in) operating
activities
(1,737)
(3,272)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
-
-
61
61
(116)
(179)
(e) investments
-
-
(f)
-
-
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
other non-current assets
Page | 13
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
2.2
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
24
2.6
Net cash from / (used in) investing
activities
(55)
(94)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
253
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(103)
(147)
3.5
Proceeds from borrowings
14,149
19,224
3.6
Repayment of borrowings
(11,006)
(15,916)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
(74)
(135)
3.10
Net cash from / (used in) financing
activities
2,966
3,279
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
864
2,125
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(1,737)
(3,272)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(55)
(94)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
2,966
3,279
Page | 14
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
4.5
Effect of movement in exchange rates on
cash held
4.6
Cash and cash equivalents at end of
period
5.
Reconciliation of cash and cash
equivalents
-
-
2,038
2,038
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
2,038
864
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
2,038
864
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
107
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
127
5.1
Bank balances
5.2
Current quarter
$A'000
Note: 6.1 This is made up of amounts paid to the directors including salary, directors’ fees, consult