March 2025 Quarter Activities and Cashflow Reports
Released
Released
Announcement PDF
ASX Announcement
30 April 2025
ASX: MKR
March 2025 Quarterly Activities Report
Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide the
following report on its activities during the quarter ending 31 March 2025.
Highlights
•
Wonawinta silver reserve update underway and due for release during May
2025.
•
Hong Kong based lender refinance process ongoing and progressing.
•
Precious metals production remains on schedule for 2025 calendar year
commencement (will be confirmed alongside debt refinance).
•
Manuka’s New Zealand subsidiary Trans-Tasman Resources Limited (TTR)
released an Updated Pre-feasibility Study (PFS)1 and Economic Impact
Assessment (EIA)2 for its Taranaki VTM project.
•
The PFS and EIA outlined a robust economic business case highlighted by
operating costs of US$27.20/tonne concentrate, average annual EBITDA of
US$312M and a post-tax NPV10 of US$1.26B with an IRR of 39% based on an
initial capital investment of US$602M (NZ$1B).
•
The Project is one of national significance for New Zealand and supports the
Government’s objective to double mineral export earnings from NZ$1.5B to
NZ$3B per annum by 2035. The Taranaki VTM Project is forecast to generate
NZ$854M export revenue per annum representing over 50% of the targeted
increase and making it one of the country’s top 12 exporters.
•
Taranaki VTM Project Fast Track Approvals application (FTA)3 lodged on 15
April 2025 for consideration by an expert panel under the Fast Track Approvals
Act 2024 (Fast Track Act).
Post Quarter End
TTR submitted its Fast Track Approvals application (FTA) on 15 April 2025 for consideration by
a panel whose members have relevant knowledge and expertise in mining projects, to consider
1 ASX Announcement 26 March 2025: Taranaki VTM Project Delivers Extremely Robust Pre-Feasibility Economics.
2 ASX Announcement 2 April 2025: Economic Impact Assessment Confirms the National Significance of the Taranaki VTM
Project.
3 ASX Announcement 16 April 2025: Manuka subsidiary Trans-Tasman Resources Limited Lodges Fast Track Application for its
Taranaki VTM Project.
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
the approvals of the Marine and Discharge Consents and apply any relevant conditions.
Figure 1: Location of Resources Development Projects in New Zealand. Source: “A Minerals Strategy
for New Zealand to 2040” - January 2025
Dennis Karp, Manuka’s Executive Chairman, commented:
“This is an outstanding opportunity for Manuka investors and a huge economic boost in the
Taranaki and Whanganui regions specifically, as well as flow-on benefits for all of New Zealand.
As advised in our PFS release through the ASX on 26 March 2025, the Taranaki VTM Project
is an exciting, financially robust and potentially company-making opportunity that provides
Manuka shareholders with strategic exposure to critical minerals.
The EIA released on 2 April 2025 shows the Project is one of national significance for New
Zealand, will make a significant contribution to doubling NZ’s mineral exports to NZ$3B per
Page | 2
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
annum by 2035 and be one of the country’s top 12 export earners. The Taranaki VTM Project
is forecast to generate NZ$854M revenue per annum representing over 50% of the targeted
increase in mineral exports.
With the updated PFS complete and our Fast Track Approvals application lodged, we are now
looking forward to progressing the Project through the FTA approvals process and turning our
attention to workstreams related to Project delivery and execution”
Manuka’s Maiden Silver Ore Reserve (released in October 2024) and the preparation of an
Implementation Plan for Wonawinta represents a major milestone for the Company and
supports a potential restarting of silver mining and processing operations. We are in the process
of updating the Silver Ore Reserve and expect to release the update during May 2025.Our
process plant at Wonawinta has been kept in excellent condition and on active care &
maintenance since the processing of gold from stockpiles hauled from Mt Boppy, ceased in
February 2024 and therefore stands ready to come back online at short notice.
Manuka continues to progress with the evaluation of installing a processing plant at its 100%
owned Mt Boppy gold project, with the aim of restarting gold production. During the quarter
metallurgical testwork was undertaken on samples collected from the historic tailings facility.
Background
Manuka Resources Limited (“Manuka” or the “Company”) is an ASX-listed producer, developer
and explorer with a 100% interest in two fully permitted precious metal mines located in the
Cobar Basin NSW as well as a world-class VTM iron sands resource located in New Zealand.
Operations at both Mt Boppy and Wonawinta continued in a state of care and maintenance,
which had initially been introduced during the March 2024 quarter.
Following the passage of the NZ Fast Track Act, TTR is now targeting the lodgement of its
application for its Taranaki VTM iron sands project under the Fast Track Act this quarter. In
parallel, the Company is also pursuing the return to profitable gold and silver production from
its NSW assets and the generation of free cash flow to self-fund further project development
and exploration.
Mt Boppy Gold Mine
The initial ~3.5-year Mt Boppy mine plan4 focuses on reprocessing the rock dumps and tailings,
as well as re-opening the open cast operation.
The establishment of a processing facility at Mt Boppy and future commencement of production
remains contingent on ongoing metallurgical testwork results and project finance being secured
in conjunction with the ongoing process to refinance the existing senior debt facility.
Wonawinta Silver Mine
Wonawinta was previously Australia’s largest primary silver mine and processing plant,
producing approximately 3Moz silver from between 2012 to 2014. Most recently, between April
2020 and December 2023, the processing plant at Wonawinta was returned to operation, initially
treating gold ores from the Mt Boppy Mine located 150km to the north, before transitioning to
treating silver ores from stockpiles located on the Wonawinta ROM from previous mining during
4 ASX Announcement 30 September 2024
Page | 3
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
2022. Prior to entering care and maintenance in Feb 2024, it had again processed Mt Boppy
gold bearing material from waste dumps and tailings.
Part of the historic metallurgical issues encountered during previous production, included the
blinding of the carbon recovery train by the high clay bearing ores. Between October 2022 and
February 2023, a trial campaign of processing silver bearing oxide stockpiles on the ROM at
Wonawinta was undertaken by the Company. During the trial period, Manuka completed a series
of modifications and innovations to the Wonawinta processing facility including the introduction
of a de-slime circuit to remove deleterious fine clays from the ore and increase Ag feed grade
into the CIL circuit.
This metallurgical test work, confirmed by production data, saw an uplift in silver feed grades to
the leach circuit by up to 100%. Higher grades and lower clays increased silver loadings onto
carbon. This testwork has been reviewed during the current quarter, and further testwork has
been undertaken to refine the flow process, equipment selection and overall Ag recovery.
Suitable vendors have been approached for the re-engineering of the deslime circuit, and capital
costs to effect these improvements detailed.
Based on this work and continued positive movements in the price of silver, the Company has
been making steady progress towards costing and progressing a restart of its Wonawinta silver
project. During the quarter the Wonawinta Ore Reserve estimate has been reviewed with
updated capital and operating cost estimates. The outcome of this work will be a pre-Feasibility
study (PFS) level with revised Ore Reserves, and an associated Implementation Plan5 and will
be reported during Q2 2025.
Currently the September 2024 Ore Reserve represents only 13% of the defined Mineral
Resource of 38.3Mt at 41.3g/t Ag for 51Moz of silver6. Detailed drill planning has been
undertaken during the quarter that will support conversion of in pit Inferred Resources to JORC
compliant Indicated Resource classification.
Table 1: Wonawinta Silver Project Ore Reserve (Sept 2024)
Classification
Mt
g/t Ag
Moz
Proved
0.8
50.8
1.3
Probable
4.1
54.3
7.1
Total
4.8
53.8
8.4
Note: Tonnes and Grade are rounded. Discrepancies in calculated Contained Metal is due to rounding.
The Wonawinta plant, having been in production as recently as January 2024 and on an active
care and maintenance program since, stands ready for a rapid restart of production subject to
completing installation and commissioning of the upgraded front end material handling and
deslime circuit.
The Wonawinta deposit, a predominantly carbonate-hosted Ag-Pb-Zn deposit with similarities
to the Mississippian Valley Type (“MVT”) of deposit, is prospective along strike and down dip for
silver, lead and zinc mineralization as evidenced by proof-of-concept drilling completed in 20217.
5 ASX Announcement 29 October 2024
6 ASX Announcement 1 April 2021
7 ASX Announcement 1 June 2021
Page | 4
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Notably, Wonawinta is the only primary silver Ore Reserve in Australia with all mining approvals
current and a process plant fully constructed. The mine infrastructure is also strategically located
within trucking distance of a number of significant undeveloped deposits within the prolific metal
bearing Cobar basin.
Taranaki VTM Iron Sands Project
Manuka holds a 100% interest in the Taranaki VTM Iron Sands Project via its wholly owned
subsidiary TTR. Located offshore in the South Taranaki Bight (STB), within New Zealand’s
Exclusive Economic Zone (EEZ), the project comprises a 3.2Bt vanadiferous titanomagnetite
(VTM) iron ore resource8 at 10.17% Fe2O3, 0.05% V2O5 (containing 1.6Mt V2O5) and 1.03% TiO2
(Table 2), ranking it as one of the largest drilled vanadium projects globally. Indicated Resources
comprise 65.7% of the total Resources with the balance being Inferred.
Table 2: Taranaki VTM Iron Sands Project Mineral Resource
Resource
Bt
Fe2O3 (%)
TiO2 (%)
V2O5 (%)
Indicated
2.1
10.45
1.06
0.05
Inferred
1.1
9.64
0.99
0.04
Total
3.2
10.17
1.03
0.05
TTR has granted mineral mining permit MMP55581 within the EEZ containing 1.88Bt VTM
resource where the current PFS mine plan can deliver production of 5Mt export concentrates a
year grading 56-57%Fe, 0.5%V2O5 and 8.5%TiO2. TTR’s adjoining mineral exploration permit,
MEP54068 inside the 12Nm limit within the Coastal Management Area (CMA), contains a
reported additional 1.29Bt VTM iron sands resource.
On 26 March 2025 Manuka release the 2025 Pre-feasibility Study (PFS)9 and the NZIER
Economic Impact Assessment (EIA)10 on 2 April 2025 for the Project.
The PFS and EIA outlined a robust economic business case underpinned by a 3.2Bt Resource
(Table 2) highlighted by operating costs of US$27.20/tonne concentrate, average annual
EBITDA of US$312M over a 20-year initial mine life and a post-tax NPV10 of US$1.26B with an
IRR of 39% based on an initial capital investment of US$602M (NZ$1B) including US$84.4M
contingency.
Based on these figures, the Project is forecast to:
•
Increase New Zealand’s annual GDP by NZ$265 million, create an estimated 1,635 new
high value jobs across the economy with 1,123 being in the Taranaki Whanganui region;
•
Generate total export earnings of NZ$854 million per annum (NZ$658 million Iron Ore and
NZ$196 million vanadium pentoxide (V2O5)) and be one of New Zealand’s top 12 principal
8 ASX Announcement 1 March 2023: Maiden Vanadium Resource at Taranaki VTM Iron Sand Project in New Zealand.
9 ASX Announcement 26 March 2025: Taranaki VTM Project Delivers Extremely Robust Pre-Feasibility Economics.
10 ASX Announcement 2 April 2025: Economic Impact Assessment Confirms the National Significance of the Taranaki VTM
Project.
Page | 5
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
export earners; and
•
Pay royalties of between NZ$36 million and NZ$54 million and contribute NZ$91 million
and NZ$136 million corporate tax per annum to the New Zealand Government.
Importantly, the Project will deliver substantial benefits to the Taranaki and Whanganui regions
with over 300 new full-time local jobs and NZ$238M per annum expenditure injected into the
local economy boosting Taranaki’s GDP by NZ$222 million.
The Project is one of national significance for New Zealand whose stated objective is to double
mineral export earnings from NZ$1.5B to NZ$3B per annum over the next decade. The Taranaki
VTM Project is forecast to generate NZ$854M revenue per annum representing over 50% of
the targeted increase.
TTR’s Taranaki VTM Project is listed in Schedule 2 of the New Zealand Fast Track Approvals
Act 2024 (Fast Track Act) to be considered by an expert panel for final approvals to develop.
Schedule 2 projects, including TTR’s, are considered to meet the Fast Track Act’s purpose
including being projects of regional or national significance.
Fast Track Approvals (FTA) applications opened on 7 February 2025 and TTR commenced
preparing its application to the EPA to have its VTM project’s Marine and Discharge
environmental consents approved. TTR submitted its FTA application, post Quarter end, on 15
April 202511 for consideration by an expert panel whose members have relevant knowledge and
expertise in mining projects, to consider the approval of the Marine and Discharge Consents
and apply any relevant conditions.
Fast Track approval is subject to compliance with the EEZ Act that includes comprehensive
environmental safeguards to protect the STB environment and is not a shortcut to avoid
environmental best practice and compliance. TTR’s application includes 109 operating
conditions and a set of comprehensive management plans to ensure there are no adverse
effects on the marine environment.
New Zealand’s Critical Minerals List, the Minerals Strategy for New Zealand 2040 (released on
31 January 2025) and the GNS Report on the country’s potential economic mineral deposits
(released in August 2024) include vanadium and titanium and the offshore Taranaki VTM
deposits in the STB controlled 100% by TTR. The MBIE reports provide the government with
insight and facts as to the potential for the development of these mineral resources in New
Zealand.
Exploration Activities
The Company continued surface exploration activities during the quarter, with the focus shifting
to the Wonawinta silver project.
Work centred on assessing the status of the current drilling database from the existing 2021
MRE that provides the block model for the basis for Ore Reserve estimation commensurate to
re-establishing mining operations. In particular infill and follow-up drilling programmes have
been designed for Inferred resource conversion to Indicated resource classification. Exploration
11 ASX Announcement 16 April 2025: Manuka subsidiary Trans-Tasman Resources Limited Lodges Fast Track Application for its
Taranaki VTM Project.
Page | 6
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
targets for mineral zones that would augment the current MRE are in the process of being
reviewed.
Mining Development Activities
In accordance with ASX Listing Rule 5.3.1 cash outflows for the quarter in relation to exploration
development activities were $0.201 million (refer items 1.2(a) and 2.1(d) of the Appendix 5B).
The cost related to salaries and wages for geology, as well as licencing fees, metallurgical test
work and assays.
Mining Production Activities
In accordance with ASX Listing Rule 5.3.2 cash outflows for the quarter in relation to mining
production and development activities were $0.100 million (refer Item 1.2(b) and 1.2(c) of the
Appendix 5B) and comprised the following:
•
Development
$0.015 million
•
Crushing contractors
$0.053 million
•
Processing
$0.032 million
Cashflow and Hedging
The Company did not have any open hedge contracts as at 31 March 2025.
Total borrowings as at 31 March 2025 were A$38.94 million. Unused facilities available at
Quarter end were A$1.73 million and the cash balance was $0.824 million.
In accordance with ASX Listing Rule 5.3.5, during the quarter, the Company made cash
payments of $0.138 million to related parties and their associates (refer items 6.1 and 6.2 of the
Appendix 5B). This was the aggregate amount paid to the directors including salary, directors’
fees, consulting fees and superannuation.
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
Tel. 02 7253 2020
Admin@manukaresources.com.au
Page | 7
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Mining Tenements
In accordance with ASX Listing Rule 5.3.3, the following information is provided for the
quarter ended 31 March 2025.
Wonawinta Silver Project tenements are located approximately 90km to the south of
Cobar, NSW, and comprise one (1) granted mining lease and seven (7) granted
exploration licenses as below, plus processing plant and associated infrastructure.
Tenement
ML1659
EL6482
EL7345
EL6155
EL6302
EL7515
EL6623
EL8498
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Mt Boppy Gold Project tenements are located approximately 45km east of Cobar,
NSW, adjacent to the Barrier Highway. The Project comprises four gold leases, two
mining leases, one mining purpose lease and one exploration licence which
encompasses the MLs and extends the project area to the south.
Tenement
GL3255
GL5836
GL5848
GL5898
ML311
ML1681
MPL240
EL5842
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Taranaki VTM Iron Sand Project tenements are located offshore in the South Taranaki
Bight of the North Island, New Zealand. Tenements acquired as a result of the acquisition
of TTR (ASX 11 November 2022) comprise one granted mining permit and one granted
exploration permit.
Tenement
MMP55581
MEP54068
Percentage held / earning
100%
100%
Change during Quarter
-
There were no tenements disposed of and no farm-in or farm-out agreements entered into during
the quarter.
About Manuka Resources Limited
Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration
company with key gold and silver assets, both permitted for mining and production,
Page | 8
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
located in the Cobar Basin (NSW). Manuka is also the owner of an offshore vanadium
and titanium bearing iron sands project in the South Taranaki Bight of New Zealand.
The Company is working towards restarting precious metals production during calendar
2025.
The Mt Boppy Gold Mine (Cobar Basin, NSW)
The Mt Boppy gold mine is located 43 km east of Cobar, in the Central West region of
New South Wales. A resource update was released on ASX on 16 April 2024.
The Company has to date processed its stockpiles and gold mineralised waste product
through its Wonawinta plant. Manuka are currently evaluating metallurgical test results
and scoping additional work to assist the strategy of establishing of a fit-for-purpose,
on-site crush-screen-mill-float facility to enhance the economics of the Mt. Boppy Mine
and the value of near-mine prospects. The Mt Boppy site includes a 48-person mine
camp and is fully permitted for the proposed processing plant and on-site production.
The Wonawinta Silver Mine (Cobar Basin, NSW)
Previously Australia’s largest primary silver producer, Wonawinta produced
approximately 3 million ounces of silver during 2012-2013, and an additional 500,000oz
of silver in 2022. The mine hosts a significant Resource12 - including stockpiles and
shallow oxide material, Wonawinta contains total Resources of 38.8 million tonnes at
42 g/t Ag for 52.4 million ounces. Furthermore, on 29 October the Company released
its maiden Ore Reserve of 4.8Mt13 at 53.8g/t Ag containing 8.4Moz of silver comprising:
-
Proved Ore Reserves of 0.8Mt at 50.8g/t Ag; and
Probable Ore Reserves of 4.1Mt at 54.3g/t Ag.
The Wonawinta processing plant has a nameplate capacity of approximately 850,000
tpa. The Company is reviewing the potential of recommencing operations at Wonawinta,
taking advantage of the strengthening silver price environment.
The Taranaki VTM Project (South Taranaki Bight, New Zealand)
Manuka is the 100% owner of the Taranaki VTM (vanadium titanomagnetite) iron sands
Project via its subsidiary Trans-Tasman Resources (TTR). The 3.2Bt Taranaki VTM
Project Resource was released on ASX on 1 March 2023.
The Project is located 22km to 36km offshore in New Zealand’s EEZ, or Exclusive
Economic Zone, outside the 12 nautical limit from the shoreline, in waters ranging
between 20 to 50 metres depth and has a granted mining permit, MMP55581, permitting
production of 5Mtpa. TTR lodged its Fast Track application for its marine discharge
consent to the New Zealand government on 15 April 2025. On granting of final
government approvals to operate the Company will complete its Bankable Feasibility
12
13
ASX Release 1 April 2021
Arithmetic errors may be present due to rounding
Page | 9
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
Study (BFS) on the Project. The Project is anticipated to sit in the lowest quartile of the
iron ore production cost curve.
Compliance Statements
The information in this announcement that relates to previously reported Exploration Results, Exploration
Targets, Mineral Resources, Ore Reserves, Production Targets and Financial Forecasts is extracted from
the Company’s ASX announcements and are available to view on the Company’s website. The Company
confirms that, other than mining depletion, it is not aware of any new information or data that materially
affects the information included in the original announcements and, in the case of estimates of Mineral
Resources and Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant announcement continue to apply and have not materially changes. The
Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially altered.
Important Information
This report includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other
similar expressions are intended to identify forward-looking statements. Such statements involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company, and which may cause actual results, performance or achievements to differ
materially from those expressed or implied by such statements. Forward-looking statements are provided
as a general guide only and should not be relied on as an indication or guarantee of future performance.
Given these uncertainties, recipients are cautioned to not place undue reliance on any forward-looking
statement. Subject to any continuing obligations under applicable law, the Company disclaims any
obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in
this report to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based. No Limited Party
or any other person makes any representation or gives any assurance or guarantee that the occurrence
of the events expressed or implied in any forward-looking statements in the report will occur.
Page | 10
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
APPENDIX 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Manuka Resources Ltd
ABN
Quarter ended (“current quarter”)
80 611 963 225
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 March 2025
Current quarter
$A’000
Year to date
(9 months)
$A’000
(4)
-
(a) exploration & evaluation
(217)
(658)
(b) development
(15)
1
(c) production
(85)
(568)
(d) staff costs
(675)
(2,101)
(e) administration and corporate costs
(552)
(1,563)
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
-
-
1.5
Interest and other costs of finance paid
617
339
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
(307)
40
1.9
Net cash from / (used in) operating
activities
(1,238)
(4,509)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
-
-
(c) property, plant and equipment
46
107
(d) exploration & evaluation
16
(163)
(e) investments
-
-
(f)
-
-
(a) entities
(b) tenements
other non-current assets
Page | 11
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
2.2
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
24
2.6
Net cash from / (used in) investing
activities
62
(32)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
253
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
(147)
3.5
Proceeds from borrowings
4,426
23,650
3.6
Repayment of borrowings
(4,591)
(20,507)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
128
(7)
3.10
Net cash from / (used in) financing
activities
(38)
3,241
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
2,038
2,125
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(1,238)
(4,509)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
62
(32)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(38)
3,241
Page | 12
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
824
824
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
824
2,038
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
824
2,038
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
75
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
63
Current quarter
$A'000
Note: 6.1 This is made up of amounts paid to the directors including salary, directors’ fees, consulting fees and
superannuation.
Note: 6.2 This is made up of amounts paid to the directors including consulting fees in respect of exploration activities.
Page | 13
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02 7253 2020
www.manukaresources.com.au
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Add notes as necessary for an understanding
of the sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
40,676
38,943
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
40,676
38,943
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing facilities
have been entered into or are proposed to be ente
Share your feedback
Discover