Mt Boppy Crushing, Screening and Haulage Underway
Released
Released
Announcement PDF
ASX Announcement
21 April 2026
ASX: MKR
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225 Tel 02- 7253 2020 www.manukaresources.com.au
MT BOPPY CRUSHING, SCREENING & HAULAGE UNDERWAY AS
MANUKA ADVANCES TOWARD PRODUCTION THIS QUARTER
Majority of development milestones now complete, commissioning
and first production targeted by June 2026
Manuka Resources Limited (ASX: MKR) (Manuka or the Company) is pleased to advise that
crushing, screening and haulage activities from its Mt Boppy gold project are now underway,
marking a further key step toward the planned restart of production at its Wonawinta processing
facility.
Following the successful completion of its Care and Maintenance program (as announced 9
March 2026), the Company continues to progress through the final execution phase, with
commissioning and first production targeted by June 2026.
Key Points
• Screening and crushing of Mt Boppy gold bearing plant feed commenced in March
2026;
• Haulage to Wonawinta scheduled to commence 22 April 2026;
• Mt Boppy plant feed to support initial commissioning phase (May/June 2026)
• This phase of operations expected to generate early revenue ahead of silver
production
• Installation of silver deslime circuit to support transition to primary silver processing
• Production timetable remains on track for Q2 2026 first production
Executive Chairman, Dennis Karp, commented.
“This marks another key milestone as Manuka advances toward production. With crushing,
screening and haulage now underway, we are nearing the final stages of commissioning.
Initial processing is focused on Mt Boppy gold bearing materials, closely followed by silver
production from the Wonawinta silver ores. The Company continues to systematically
execute its restart plan, targeting first production in Q2.”
Authorised for release by the Board of Directors of Manuka Resources Limited
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
Tel. +61 2 72532020
Page | 2
Production Timetable and Milestones
Progressing through final execution phase toward first production.
Completed
✅ Refinancing secured
✅ All major approvals in place and in good standing
✅ Care & maintenance phase completed
✅ Key on-site management team and workforce secured
✅ Processing equipment upgrades (deslime / dewatering circuit) nearing
delivery
June 2026
quarter
Reserve upgrade and revised mine-plan at Wonawinta (May 2026)
Gold bearing ROM stockpile continues to build at Wonawinta
Haulage from Mt Boppy underway (April)
Commissioning and ramp-up of silver and gold-bearing ROM stockpiles
First gold processing commences (May/June)
Sept 2026
quarter
☐ Plant upgrade equipment installed and commissioned
☐ First silver production and sales
☐ Commencement of mining silver ores
☐ Ramp-up to nameplate production
☐ Steady state production and cash flow generation
Mt Boppy – Crushing and Screening Activities April 2026