Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide the
following report on its activities during the quarter ending 31 March 2024.
Highlights
During the Quarter
•
The Company investigated the economic and strategic benefits of establishing
fit-for-purpose ore processing and gold doré production facility at Mt Boppy.
•
Accordingly, the transporting to, and processing of, Mt Boppy ore through the
Company’s Wonawinta plant, located 150km south, was placed on hold.
•
Results from a sonic drilling program were received improving the confidence
level of the Mt Boppy Resource and supporting the development of a longer term
mine plan.
•
Income from the sale of 201oz gold and 2,487oz silver recovered from Mt Boppy
ore, together with funds of A$3.9 million received from a combination of
placement and SPP, were used to offset costs associated with the ramp-down of
operations and working capital requirements.
Post Quarter End
•
The Company announced the results of its Mt Boppy investigations outlining an
A$11.6M upfront capital cost and an initial 5-year mine plan to deliver an average
EBITDA of A$19M per annum commencing Q4 20241.
•
The mine plan was supported by an upgrade in the Mt Boppy Resource which
saw Measured and Indicated Resources increase to 82% of the total Resource2.
•
The Company received A$1.1M from an application made under the Australian
Government’s R&D tax incentive scheme for a successful process improvement
program undertaken to enhance silver production at Wonawinta. The Company
is targeting the release of an updated Reserve Statement for Wonawinta as a
standalone silver operation during the current quarter.
•
The Company was specifically invited to submit an application for the world-class
Taranaki VTM Iron Sands Project to be included as a Listed Project within New
Zealand’s Fast Track Consenting Bill, legislation to streamline decision making
and facilitate the delivery projects with significant regional or national benefits.
1 ASX release 15 April 2024
2 ASX release 16 April 2024
Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000
ABN 80 611 963 225
Tel 02- 7253 2020
www.manukaresources.com.au
Dennis Karp, Manuka’s Executive Chairman, commented:
“The March quarter has been one of transition and one that has seen the Company
decisively pivot its strategy toward a staged, self-sustaining growth plan.
Manuka Resources is uniquely positioned amongst its ASX peers to leverage buoyant
gold and silver markets. In the Mt Boppy and Wonawinta mines, we have a low capex
pathway to deliver near term gold and silver production and free cashflow to fund
exploration, Resource growth and mine life extension.
Looking further ahead, the invitation to apply for inclusion as a Listed Project within New
Zealand’s Fast Track Consenting Bill provides line of sight on the progressing of our
world-class Taranaki VTM Iron Sands Project
We are looking forward toward the next quarter and next 12 month with great optimism
and confidence that our strategy will deliver results for our shareholders.”
Background
Manuka Resources Limited (“Manuka” or the “Company”) an is ASX listed producer, developer
and explorer with a 100% interest in two precious metal mines located in the Cobar Basin NSW
and a world-class VTM Iron Sands Resource located in New Zealand.
The Company is pursuing a staged growth strategy that is initially focused on gold and silver
production and free cash flow generation from its NSW assets.
Operations
During the quarter, operations at Mt Boppy, and the associated processing of Mt Boppy ore at
Wonawinta, were placed on hold whilst the Company assessed the economic and strategic
benefits of establishing fit-for-purpose ore processing and gold doré production facility at Mt
Boppy and finalised a sonic drilling program to enhance confidence in the Mt Boppy Resource.
A total 201oz gold and 2,487oz silver recovered from Mt Boppy ore during the previous quarter
was sold during the quarter, generating A$724K of revenue (Table 1).
Table 1: Production Summary
Summary
Unit
March Quarter
Financial Year (YTD)
Tonnes Milled
t
-
136,728
Gold in Circuit
oz
-
-
Gold Recovered
oz
-
4,835
Gold Sold
oz
210
4,835
Silver Sold
oz
2,487
26,387
Revenues
A$’000
758
15,475
Page | 2
Sonic Drilling Program
The Company most recently produced gold by screening rock dump and tailings material at the
Mt Boppy ROM over the period May to December 2023. A decision was taken to halt operations
to allow for the derisking of the grade distribution ahead of mining the Boppy Main Waste Rock
Dump and Dry Tailings.
A 26-borehole sonic drilling evaluation was completed on the Boppy Main Waste dump and the
TSF3 impoundment including Potential Acid Forming (PAF) material overlying part of the tailings
(Figure 1). The sonic evaluation drilling has enabled sampling of the full profile of the rock and
tailings dumps, and thus assessment of the economic viability of treating crushed and screened
rock dump fines and tailings on site at Mt Boppy.
Figure 1: Drone image looking south showing the main components of the Rock Dump and
Tailings Resources in relation to the Mt Boppy open pit.
Updated Mineral Resource Estimate for Mt Boppy
As result of the sonic drilling program, Manuka was able to release an updated and enhanced
Mineral Resource Statement for Mt Boppy (post quarter end) that saw Measured and Indicated
Resource increase to 82% of the total Resource3 (Table 2).
Importantly, a high-grade sub-component of the Resource measuring 1.8Mt at 1.74 g/t and was
identified as the basis for developing an updated mine plan for Mt Boppy.
Mt Boppy was previously one of NSW’s richest gold mines having produced ~500,000 oz gold
at ~15 g/t since the early 1900’s. The existing open pit extends to a depth of ~70m, with historic
underground workings extend a further ~100m. The deposit is open at depth and along strike.
Cash flows generated from production at Mt Boppy will fund aggressive near pit exploration with
the aim of identifying high grade ore shoots such as those previously mined.
3 ASX release 16 April 2024
Page | 3
Table 2 - Mt Boppy Global Resource by Classification
Tonnes
Grade
Contained
Contained
kt
g/t Au
koz
%
Measured
107
5.25
18.0
11%
Indicated
3,127
1.16
116.5
71%
M+I Sub Total
3,233
1.29
134.5
82%
Inferred
1,046
0.87
29.4
18%
Total
4,279
1.19
163.9
100%
Resource Classification
Updated Mt Boppy Mine Plan and Production Strategy
On the back of the successful sonic drilling program and updated Mineral Resource, the
Company finalised its updated mine plan and economic assessment of Mt Boppy on the basis
of installing for-purpose ore processing and gold doré production facility on-site.
Highlights of the assessment include4:
•
Low Upfront Capital Cost of A$11.6M (including contingency)
•
First gold doré production in the December Quarter of 2024
•
Initial 5-Year Mine Plan
•
~48,000oz of gold produced in doré over the initial Mine Plan
•
Forecast AISC of US$1,060/oz gold
•
High operating margin, delivering an average Annual EBITDA of A$19M
•
Pre-tax IRR = 155%
Indicative Timeline
Q2 24
Q3 24
Q4 24
Sonic Drilling and MRE Update
Relocate Generators from Wonawinta
New Tailings Dam Construction
Purchase/Transport/Installation of Plant & Equipment
Relocate Elution/Recovery Units from Wonawinta
Mt Boppy Plant Site works
Fleet Mobilisation and Mining
Mt Boppy Plant Commissioning/Production
4 ASX release 15 April 2024
Page | 4
Wonawinta Silver Project
Previously Australia’s largest primary Silver Mine, Wonawinta produced approximately 3Moz
silver from 2012 to 2013. Most recently, the process plant at Wonawinta has been used to
process ore from the Mt Boppy Mine located 150km to the north.
Between October 2022 and February 2023, a limited trial campaign of silver production at
Wonawinta was undertaken by the Company. During the trial period, the Manuka completed a
series of modifications and innovations to the Wonawinta processing facility including the
introduction of a deslime circuit to remove deleterious fine clays from the ore and increase feed
grade into the CIL circuit.
Metallurgical test work, confirmed by production data, saw an uplift in silver feed grades to the leach
circuit by up to 100%. Higher grades and lower clays increased silver loadings onto carbon. The
improvements and innovations achieved were material leading to an increase in throughput
to >1.0Mtpa of material through the plant (from nameplate capacity of 850Ktpa),
During the quarter, the Company successfully applied for a A$1.07M rebate under the Australian
Government’s R&D tax incentive scheme in respect to the performance improvement program
at Wonawinta. Funds from the rebate were received after the end of the quarter.
The Company is targeting the release of an updated Reserve Statement for Wonawinta as a
standalone silver operation during the current quarter with a view to restarting silver production
in 2025 with the support of cashflows from Mt Boppy.
The project has a total Resource of 38.3Mt at 41.3g/t Ag for 51Moz including a higher-grade
component of 4.5Mt at 97g/t Ag for 14Moz5. Additionally, the Wonawinta deposit, a Mississippian
Valley Type (“MVT”) deposit, is prospective down dip for Lead and Zinc as evidenced by proofof-concept drilling completed in 20216.
Taranaki VTM Iron Sands Project
Manuka’s via its wholly owned subsidiary, Trans-Tasman Resources Limited (“TTR”) hold a
100% interest in the Taranaki VTM Iron Sands Project. Located in offshore within New
Zealand’s Exclusive Economic Zone, the project comprises a 3.2Bt Resource7 at 10.17% Fe2O3,
1.03% TiO2 and 0.05% V2O5 (1.6Mt V2O5), ranking it as one of the largest drilled vanadium
projects globally, and a granted mineral mining permit permitted the production of 5Mtpa.
During the quarter, the recently elected New Zealand government introduced, as part of its 100
day plan, the Fast Track Consenting approvals bill (“the Bill”) with the objective of providing a
streamlined decision-making process to facilitate the delivery of natural resource and
infrastructure development projects with significant regional or national benefits Post quarter
end, the Company was specifically invited to submit an application for the world-class Taranaki
VTM Iron Sands Project to be included as a Listed Project within the bill.
An advisory group has been established by the Government to make recommendations to the
relevant Ministers, who will then make decisions on what projects to include in the Bill. These
projects will be added to the Bill either through the Environmental Select Committee process or
later in the Parliamentary process. The Company is currently preparing an application for the
Taranaki VTM Project to be included in the Bill.
5 ASX release 1 April 2021
6 ASX release 1 June 2021
7 ASX release 1 March 2023
Page | 5
Mining Development Activities
In accordance with ASX Listing Rule 5.3.1 cash outflows for the quarter in relation to exploration
development activities were $0.049 million (refer items 1.2(a) and 2.1(d) of the Appendix 5B).
The cost where primarily related to the completion of the sonic drilling program.
Mining Production Activities
In accordance with ASX Listing Rule 5.3.2 cash outflows for the quarter in relation to mining
production and development activities were $1.027 million (refer Item 1.2(b) & 1.2(c) of the
Appendix 5B) and comprised the following:
•
Crushing contractors
$0.32 million
•
Hauling contractors
$0.48 million
•
Processing
$0.22 million
Cashflow and Hedging
During the quarter, the Company realised A$734K revenue from the sales of 201oz gold and
2,487oz silver recovered from Mt Boppy during the previous quarter. Net operating cashflow for
the period was (A$3.03M).
The Company did not have any open hedge contracts as at 31 March 2024.
During the quarter, the Company issued, or agreed to issue 99.76 million shares, to raise
A$3.9M for working capital purposes and the conversion of A$3.1M payable principal and
interest into equity. Securities requiring shareholder approval, as detailed in the 29 February
2024 Notice of Meeting were approved at an EGM held on 2 April 2024.
The principal amount outstanding at Quarter end to the Company’s senior secured lender,
TransAsia Private Capital (TA) was US$8.0 million and as advised in the previous Quarterly,
has been extended for repayment on 30 September 2024.
Total borrowings as at 31 March 2024 were A$27.65 million. Unused facilities available at
Quarter end were A$2.022 million and the cash balance was $40,254.
In accordance with ASX Listing Rule 5.3.3, during the quarter, the Company made cash
payments of $0.123 million to related parties and their associates (refer items 6.1 and 6.2 of the
Appendix 5B). This was the aggregate amount paid to the directors including salary, directors’
fees, consulting fees and superannuation.
This announcement has been approved for release by the Board of Manuka Resources Limited.
For further information contact:
Dennis Karp
Executive Chairman
Manuka Resources Limited
Tel. 02- 7253 2020
Media Contact
Ben Henri
M+C Partners
Tel. 0473 246 040
Page | 6
Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended
31 March 2024.
Wonawinta Silver Project tenements are located approximately 90km to the south of
Cobar, NSW, and comprises one (1) granted mining lease and seven (7) granted
exploration licences as below, plus processing plant and associated infrastructure.
Tenement
ML1659
EL6482
EL7345
EL6155
EL6302
EL7515
EL6623
EL8498
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Mt Boppy Gold Project tenements are located approximately 45km east of Cobar,
NSW, adjacent to the Barrier Highway. The Project comprises four gold leases, two
mining leases, one mining purpose lease and one exploration licence which
encompasses the MLs and extends the project area to the south.
Tenement
GL3255
GL5836
GL5848
GL5898
ML311
ML1681
MPL240
EL5842
Percentage held / earning
100%
100%
100%
100%
100%
100%
100%
100%
Change during Quarter
-
Taranaki VTM Iron Sand Project tenements are located offshore in the South Taranaki
Bight of the North Island, New Zealand. Tenements acquired as a result of the acquisition
of TTR (ASX 11 November 2022) comprise one granted mining permit and one granted
exploration permit.
Tenement
MMP55581
MEP54068
Percentage held / earning
100%
100%
Change during Quarter
-
There were no tenements disposed of during the Quarter.
Page | 7
About Manuka
Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration company with
key gold and silver assets located in the Cobar Basin, central west New South Wales and
offshore vanadium bearing iron sands in the South Taranaki Bight of New Zealand. These
projects include:
The Mt Boppy Gold Mine (Cobar Basin, NSW)
The Mt Boppy gold mine is located 43 km east of Cobar, in the Central West region of New
South Wales. The current Mt Boppy Mineral Resource8 is estimated at 4.3Mt at 1.19 g/t Au and
comprises a mix of oxidised and transitional/fresh in-ground mineralisation, mineralised rock
dumps and mineralised tailings.
The Company has to date processed its stockpiles and gold mineralised waste product through
its Wonawinta plant. Manuka are currently pursuing a strategy of establishing of a fit-forpurpose, on-site crush-screen-mill-float facility to enhance the economics of the Mt. Boppy Mine
and the value of near-mine prospects. The Mt Boppy site includes a 48-person mine camp and
is fully permitted for the proposed processing plant and on-site production.
Mt Boppy Gold mine
The Wonawinta Silver Mine (Cobar Basin, NSW)
Previously Australia’s largest primary silver producer, Wonawinta produced approximately 3
million ounces of silver during 2012-2013, and an additional 500,000oz of silver in 2022. The
mine hosts a significant Resource9 - including stockpiles and shallow oxide material, Wonawinta
contains total Resources of 38.8 million tonnes at 42 g/t Ag for 52.4 million ounces. Within this
there is a higher-grade component of 4.5 million tonnes at 97 g/t Ag for 14 million ounces.
The Wonawinta processing plant has a nameplate capacity of approximately 850,000 tpa. The
Company is reviewing the potential of recommencing operations at Wonawinta, taking
advantage of the strengthening silver price environment.
8 ASX release 16 April 2024
9 ASX release 1 April 2021
Page | 8
Wonawinta Silver Mine
The Taranaki VTM Project (South Taranaki Bight, New Zealand)
Manuka is the 100% owner of the Taranaki VTM (vanadium titanomagnetite) Iron Sands Project.
The Project sits in the lowest quartile of the iron ore production cost curve.
The Taranaki VTM Project comprises a 3.2Bt Resource10 at 10.17% Fe2O3, 1.03% TiO2 and
0.05% V2O5 (1.6Mt V2O5) ranking it as one of the largest drilled vanadium projects globally. The
Project is located 22 km to 36 km offshore in New Zealand’s EEZ, or Exclusive Economic Zone,
outside the 12 nautical limit from the shoreline, in waters ranging between 20 to 50 metres depth
and has a granted mining license, MP55581, permitting production of 5Mtpa. On granting of
final government approvals to operate the Company will complete its Bankable Feasibility Study
on the Project.
Location of Taranaki VTM Project
10ASX release 1 March 2023
Page | 9
Compliance Statements
The information in this presentation that relates to previously reported Exploration Results, Exploration
Targets, Mineral Resources, Ore Reserves, Production Targets and Financial Forecasts is extracted from
the Company’s ASX announcements noted in the text of the presentation and are available to view on
the Company’s website. The Company confirms that, other than mining depletion, it is not aware of any
new information or data that materially affects the information included in the original announcements
and, in the case of estimates of Mineral Resources and Ore Reserves, that all material assumptions and
technical parameters underpinning the estimates in the relevant announcement continue to apply and
have not materially changes. The Company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially altered.
Important Information
This report includes forward-looking statements and comments about future events, including the
Company’s expectations about the performance of its businesses. Forward-looking words such as
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”, “target” or other
similar expressions are intended to identify forward-looking statements. Such statements involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company and which may cause actual results, performance or achievements to differ
materially from those expressed or implied by such statements. Forward-looking statements are provided
as a general guide only and should not be relied on as an indication or guarantee of future performance.
Given these uncertainties, recipients are cautioned to not place undue reliance on any forward-looking
statement. Subject to any continuing obligations under applicable law, the Company disclaims any
obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in
this report to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based. No Limited Party
or any other person makes any representation, or gives any assurance or guarantee that the occurrence
of the events expressed or implied in any forward-looking statements in the report will occur.
Page | 10
APPENDIX 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Manuka Resources Ltd
ABN
Quarter ended (“current quarter”)
80 611 963 225
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 March 2024
Current quarter
$A’000
Year to date
(9 months)
$A’000
522
14,779
(a) exploration & evaluation
(2)
(5)
(b) development
1
(143)
(c) production
(1,027)
(10,255)
(d) staff costs
(2,223)
(6,435)
(383)
(1,768)
(e) administration and corporate costs
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
-
-
1.5
Interest and other costs of finance paid
20
(448)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
62
298
1.9
Net cash from / (used in) operating
activities
(3,031)
(3,978)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
(120)
(7)
(d) exploration & evaluation
(47)
(809)
-
-
20
(20)
(e) investments
(f)
other non-current assets
Page | 11
2.2
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
(24)
2.6
Net cash from / (used in) investing
activities
(147)
(860)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3,895
4,942
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(247)
(307)
3.5
Proceeds from borrowings
1,439
4,902
3.6
Repayment of borrowings
(2,135)
(4,570)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
(285)
(355)
3.10
Net cash from / (used in) financing
activities
2,667
4,612
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
552
266
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(3,031)
(3,978)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(147)
(860)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
2,667
4,612
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
41
41
Page | 12
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
41
552
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
41
552
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
60
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
63
Current quarter
$A'000
Note: 6.1 This is made up of amounts paid to the directors including salary, directors’ fees, consulting fees and
superannuation.
Note: 6.2 This is made up of amounts paid to the directors including consulting fees in respect of exploration activities.
Page | 13
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Add notes as necessary for an understanding
of the sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
29,675
27,653
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
28,675
27,653
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing facilities
have been entered into or are proposed to be entered into after quarter end, include a note
providing details of those facilities as well.
7.1
Loan facilities
7.2
Lender
Facility type
TransAsia
Private Capital
Limited
ResCap
Investments
Pty Ltd
Various
Secured Senior
Debt Facility
plus interest
Unsecured
Working
Capital Loan
Equipment
Finance
Short-term
finance
Tennant Metals
Trade Finance
stockpile facility
Various
Total Facility
2,022
Rate
Maturity
16,967
15%
30/09/2024
2,000
16%
30/09/2024
273
12%
29/04/2025
485
30%
9,951
35%
30/09/2024
3-year trade
finance facility
expiring April
2026
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
8.4
Cash and cash equivalents at quarter end (item 4.6)
8.5
Unused finance facilities available at quarter end (item 7.5)
2,022
8.6
Total available funding (item 8.4 + item 8.5)
2,063
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
0.67
(3,031)
(47)
(3,078)
41
Note: if the entity has reported positive relevant outgoings (i.e. a net cash inflow) in item 8.3, answer item 8.7 as
“N/A”. Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
Page | 14
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer:
As described in the quarterly activities report, the Company has placed operations on
hold and therefore does not anticipate incurring material operation expenditure in the
forthcoming quarters.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
The Company has A$2M in unused debt facilities available to draw if required.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
Yes. Via a combination of the unused debt facilities and other ongoing but incomplete
fund raising initiatives, the Company expects to continue its operations and meet its
business objectives.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
30 April 2024
Authorised by: ...................................................................................
Toni Gilholme – Company Secretary
On behalf of the Board of Directors
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity
that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged
to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in,
and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows
apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards
agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – e.g. Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
Page | 15
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound
system of risk management and internal control which is operating effectively.
6.
By the Company lodging this Appendix 5B, the Managing Director and CFO declare that the Appendix 5B for the relevant
quarter:
• presents a true and fair view, in all material respects, of the cashflows of the Company for the relevant quarter
Share your feedback